Project dashboard: 10 KPIs, earned value and a portfolio example

Published · Updated · 15 min read

Dylan Arnaud, founder of Datafuji

A project dashboard shows, for each active project, what was planned, what has been done and what has been spent, and from these derives the likely margin and end date. Example: a project budgeted at €220,000 that is 60% complete after €184,000 of spending will cost about €307,000 at this rate.

What is a project dashboard?

A project dashboard tells you whether each project will finish within its price and by what date, early enough to act. It reconciles four sources: the schedule, timesheets, purchases and invoicing.

It is built for businesses that sell project work: engineering firms, IT services companies, agencies, installers. Their profit is the sum of their project margins, and a single overrun can wipe it out. Construction jobs have their own rules (progress billing, retainage), covered in our construction guide.

Single-project or portfolio dashboard

Same data, different reader, different cadence; project reporting, by contrast, keeps stakeholders informed rather than steering the project.

Single-project dashboardPortfolio dashboardProject reporting
ReaderThe project managerLeadershipThe client, the steering committee
FrequencyEvery weekEvery monthAt each milestone or committee meeting
ContentTasks, milestones, risks, hours per personOne row per project: margin at completion, slippage, invoicedProgress, deliverables, risks, decisions needed
QuestionWhat do we do this week?Where do we step in this month?Where do we stand?

The portfolio view is the one SMEs most often lack: project management tools show each project well, but rarely the whole portfolio in euros. A “green, amber, red” status self-reported by the project manager belongs in reporting; on the dashboard, the color has to come from a calculation.

Which KPIs should a project dashboard track?

Ten project metrics are enough for an SME: will we make money (1 to 5), will we finish on time (6), what price are we getting for our time (7, 8), and are we invoicing what we produce (9, 10)?

KPIFormulaData sourcePitfall
1. Margin at completionSelling price − estimate at completion (EAC, what the project will have cost at the end). As a %: ÷ selling priceSigned quote, budget, timesheets, allocated purchasesTracking the monthly margin in the accounting books: on a half-finished fixed-price project, it tells you nothing.
2. Cost performance index (CPI)Earned value (work done, in budget euros) ÷ actual costBudget, progress, timesheets and purchasesAssuming progress equals budget spent: the CPI then always comes out at 1.
3. Schedule performance index (SPI)Earned value ÷ planned valueBaseline schedule, actual progressReading it as a delay in days: it measures euros of work and returns to 1 at the end of the project.
4. Actual progress and budget spentProgress measured on deliverables, compared with actual cost ÷ budgetProject manager, timesheetsEstimating it “by feel”; instead, count 0% until a work package has started and 100% once it is accepted.
5. Estimate to completeEAC − actual cost; in hours: hours at completion − hours spentCalculation, checked by the project managerConfusing it with budget − spent, which is only what is left of the budget.
6. Schedule slippageForecast end date − contractual end date, in weeksSchedule, project managerRe-forecasting the end date only at the end of the project.
7. Realized day rateFixed price ÷ days at completion, estimated as days spent ÷ actual progressQuote, timesheetsComparing it with the sold day rate without looking at what a day actually costs.
8. Utilization rateBillable hours ÷ available hoursSchedule, timesheetsAiming for 100%. Training, presales and vacation are real: define what counts as available hours, and set a realistic target for each role.
9. Invoiced vs. producedInvoiced to date − price × actual progress, project by projectInvoicing, progressLooking only at the total: a project invoiced in advance hides one that has not been invoiced yet.
10. Order backlogSigned orders not yet invoiced. In months: backlog ÷ average monthly revenueOrder management system or ERPLeaving in orders with no delivery date or put on hold by the client: the backlog looks full, yet none of it will be invoiced this quarter.

An SME just getting started can stick to KPIs 1, 4, 6 and 9. All they need is a budget per project, progress entered every month, timesheets and invoices; the others can be derived from them.

The realized day rate: what a day is really worth

On a fixed-price project, the price is fixed; the number of days is not. The “Quality tracking software” project in the example portfolio below has no purchases and is sold for €156,000 for 257 budgeted days: a sold day rate of €607.

It is 55% complete after 1,120 hours; at the same pace, it will take 2,036, and the realized day rate will fall to €536. With a day costing €490 (€70 × 7 hours), the margin drops from 19.2% to 8.6% of the price. The hourly rate calculator walks through the step from sold day rate to realized day rate.

How do you measure progress in euros? Earned value

Earned value management (EVM) converts progress into euros, so it can be compared with what has been spent and what was planned. Below 1, either of its two indices signals that the project is drifting.

It is described in the ISO 21508 standard and in U.S. government guides; Microsoft Project calls earned value the “budgeted cost of work performed” (BCWP).

Three values, as of the same date

  • Planned value (PV): the share of the budget for the work that should have been done by this date. Budget × planned progress.
  • Earned value (EV): the share of the budget for the work actually done. Budget × actual progress.
  • Actual cost (AC): what was spent to do this work. Hours spent × hourly cost rate, plus purchases and subcontracting.

The budget (BAC, budget at completion) is the cost estimated when the job was priced, not the selling price: the difference between the two is the planned margin.

The running example is the “HVAC renovation” project (heating, ventilation and air conditioning) of a fictional engineering firm. Sold for €264,000 excl. VAT, it is budgeted at 2,800 hours and €24,000 of purchases. Hours are costed at €70, the cost rate from the hourly rate calculator example, overhead included.

As of October 31, the schedule called for 85% completion; the project manager reports 60%, after 2,300 hours and €23,000 of purchases. Yet the books show a healthy margin for the month: without this reconciliation, the loss would only surface in February, too late to act.

Three bars on a scale from 0 to €220,000, the HVAC renovation project’s budget, as of October 31. Planned value: €187,000, 85% of the budget, what should have been done. Earned value: €132,000, 60%, what has been done. Actual cost: €184,000, 84% of the budget, what has been spent; its bar almost reaches the end of the planned value bar. Between earned value and planned value, the schedule variance of −€55,000 (SPI 0.71); between earned value and actual cost, the cost variance of −€52,000 (CPI 0.72). At the bottom, 84% of the budget spent, a wrong reading if taken as progress, against actual progress of 60%, measured on deliverables.Three bars on a scale from 0 to €220,000, the HVAC renovation project’s budget, as of October 31. Planned value: €187,000, 85% of the budget, what should have been done. Earned value: €132,000, 60%, what has been done. Actual cost: €184,000, 84% of the budget, what has been spent; its bar almost reaches the end of the planned value bar. Between earned value and planned value, the schedule variance of −€55,000 (SPI 0.71); between earned value and actual cost, the cost variance of −€52,000 (CPI 0.72). At the bottom, 84% of the budget spent, a wrong reading if taken as progress, against actual progress of 60%, measured on deliverables.
84% of the budget spent for 60% of the work done: actual cost has almost caught up with planned value.

The formulas, applied to the HVAC project

Budget (BAC) = 2,800 h × €70
             + €24,000
             = €220,000

Planned value = 220,000 × 85%
              = €187,000

Earned value = 220,000 × 60%
             = €132,000

Actual cost = 2,300 h × €70
            + €23,000
            = €184,000

CPI = 132,000 ÷ 184,000
    = 0.72

SPI = 132,000 ÷ 187,000
    = 0.71

EAC = 220,000 ÷ 0.72
    = €306,667

Margin at completion
    = 264,000 − 306,667
    = −€42,667

Every euro spent has produced €0.72 worth of planned work, and 71% of the work expected by this date has been done. The table completes the picture:

MetricFormulaHVAC projectWhat it means
Cost variance (CV)EV − AC−€52,000The work done cost more than planned
Schedule variance (SV)EV − PV−€55,000Less work done than planned, in euros
Estimate to complete (ETC)EAC − AC€122,667What still has to be spent
Variance at completion (VAC)BAC − EAC−€86,667The expected overrun
Margin at completionPrice − EAC−€42,667, or −16.2%Sold at a 16.7% margin, it will end at a loss

The indices are read against 1. The U.S. Department of Energy guide sums it up in one line: “Favorable is >1.0, unfavorable is <1.0.”

Which EAC formula should you use?

They all rest on the same idea: actual cost + remaining work ÷ an efficiency index. The cost guide of the GAO (U.S. Government Accountability Office) recommends calculating several and looking at the spread.

Assumption about the rest of the projectFormulaEstimate
The remaining work is done at the planned costAC + (BAC − EV)€272,000
The remaining work is done at the efficiency observed so farBAC ÷ CPI, or AC + (BAC − EV) ÷ CPI€306,667
The delay costs money tooAC + (BAC − EV) ÷ (CPI × SPI)€357,778

We use budget ÷ CPI, which the Department of Energy labels the “general” formula, and show the composite formula (CPI × SPI, third row) alongside it when it is higher. The “planned cost” formula assumes the project will suddenly start holding to its budget, and nothing points to that.

According to the GAO, among the formulas that use an index, the cumulative CPI (calculated from the start of the project) generally gives the lowest estimate, and CPI × SPI the worst case. Once a project is 20% complete, the cumulative CPI varies by less than 10%, and it most often gets worse from there.

Cost scale from €200,000 to €370,000 for the HVAC renovation project. Markers: budget €220,000 and selling price €264,000; beyond the price, the project loses money. The three estimates at completion are all beyond the price. If the rest is done at planned cost, AC + (BAC − EV): €272,000, an €8,000 loss. At the efficiency observed so far, BAC ÷ CPI, the estimate used: €306,667, a €42,667 loss. If the delay costs money too, AC + (BAC − EV) ÷ (CPI × SPI): €357,778, a €93,778 loss. The most likely range runs from €306,667 to €357,778.Cost scale from €200,000 to €370,000 for the HVAC renovation project. Markers: budget €220,000 and selling price €264,000; beyond the price, the project loses money. The three estimates at completion are all beyond the price. If the rest is done at planned cost, AC + (BAC − EV): €272,000, an €8,000 loss. At the efficiency observed so far, BAC ÷ CPI, the estimate used: €306,667, a €42,667 loss. If the delay costs money too, AC + (BAC − EV) ÷ (CPI × SPI): €357,778, a €93,778 loss. The most likely range runs from €306,667 to €357,778.
Even if the rest of the project is done at planned cost, the HVAC renovation will cost €272,000 against a price of €264,000.

The question is no longer whether the project will lose money, but how much: between €8,000 and €94,000, more likely at the high end of the range.

What earned value does not tell you

  • It is only as good as the progress measure. Measure progress on deliverables, one work package at a time; derived from hours spent, it produces a CPI that always equals 1.
  • The SPI measures a delay in euros, not in days. It returns to 1 at the end of the project, even a very late one: the GAO notes that it loses its predictive value. Track the forecast end date alongside it.
  • Before 20% completion, do not draw conclusions. The “Bottling line” project in the example portfolio below has a CPI of 0.96 at 8% completion: a signal to watch, not a verdict.
  • On time-and-materials work, it says nothing about margin. Every hour is billed: track the budget the client approved and the date you will reach it.
  • It is blind to quality. A work package redone three times shows up in actual cost, not in progress, provided the rework is booked to the project.

What does a project portfolio dashboard look like?

A portfolio dashboard fits on four pages: will the portfolio hold its margin, which projects are slipping, is the team busy enough, and are we invoicing what we produce? One row per project, calculated totals.

The example is a fictional 5-person engineering firm: 7 fixed-price projects, €996k in combined selling price, status as of October 31, made-up data, calculated metrics.

Screenshot of the “Portfolio” page of a fictional Power BI report. Three cards: margin at completion €88k (8.8% of price, plan €179k), CPI 0.88, SPI 0.84. On the left, work done by month (price × progress) and its variance to plan; on the right, each project’s planned margin and margin at completion, including HVAC at −€42.7k.Screenshot of the “Portfolio” page of a fictional Power BI report. Three cards: margin at completion €88k (8.8% of price, plan €179k), CPI 0.88, SPI 0.84. On the left, work done by month (price × progress) and its variance to plan; on the right, each project’s planned margin and margin at completion, including HVAC at −€42.7k.
The portfolio was expected to earn €179k in margin; at the current pace, it will earn €88k.

Only one row goes negative. The seven projects in detail:

ProjectPriceCPISPIPlanned marginMargin at completionSlippage
Conveyor line€72k1.121.1716.7%25.8%1 week ahead
HVAC renovation€264k0.720.7116.7%−16.2%+13 weeks
Quality tracking software€156k0.881.1019.2%8.6%0
Workshop extension€140k1.130.6418.6%28.3%+8 weeks
Electrical compliance upgrade€112k0.991.0017.9%17.2%0
Energy audit (completed)€56k0.971.0019.6%17.1%+1 week
Bottling line€196k0.960.8018.4%15.2%0
Portfolio€996k0.880.8418.0%8.8%n/a

What this report reveals in two minutes

One project explains almost everything. The HVAC renovation alone accounts for €86.7k of the €91.5k of margin the portfolio will lose (€179k planned, €87.5k at completion), or 95%. The CEO sees it at the end of October, 4 weeks before the contractual end date, not after.

A good CPI can hide a delay. The Workshop extension is spending less than planned (CPI 1.13) because it is progressing slowly (SPI 0.64): the client’s data is late, and the end date slips by 8 weeks. That is not a saving; it is revenue being pushed back.

The project running ahead calls for action. The Conveyor line (CPI 1.12, SPI 1.17) sees its margin rise to 25.8%, against 16.7% planned. With 70% of the work produced and 30% invoiced, it has €28.8k of invoices waiting to go out.

A utilization rate on target can hide lost hours. The team is at 76.1% against a 76.0% target (71.9% a year earlier). But the HVAC project has used 2,300 hours for 60% progress: at that pace, it will take 3,833 hours for the 2,800 sold. The 1,033 hours the client will not pay for still count as billable.

Portfolio metrics are calculated from totals, never by averaging project-level figures.

Seven projects, each with a bar scaled to its actual cost (outline) and its earned value (solid), in thousands of euros, and its CPI: HVAC renovation, actual cost €184.0k, earned value €132.0k, CPI 0.72; Quality tracking software, actual cost €78.4k, earned value €69.3k, CPI 0.88; Energy audit, actual cost €46.4k, earned value €45.0k, CPI 0.97; Workshop extension, actual cost €45.2k, earned value €51.3k, CPI 1.13; Conveyor line, actual cost €37.4k, earned value €42.0k, CPI 1.12; Electrical compliance upgrade, actual cost €37.1k, earned value €36.8k, CPI 0.99; Bottling line, actual cost €13.3k, earned value €12.8k, CPI 0.96. The HVAC renovation accounts for €184k of spending, the Bottling line €13k. The portfolio CPI, 389.2 ÷ 441.8, is 0.88: the right calculation. The simple average of the seven CPIs, which gives each project the same weight, shows 0.97: a trap.Seven projects, each with a bar scaled to its actual cost (outline) and its earned value (solid), in thousands of euros, and its CPI: HVAC renovation, actual cost €184.0k, earned value €132.0k, CPI 0.72; Quality tracking software, actual cost €78.4k, earned value €69.3k, CPI 0.88; Energy audit, actual cost €46.4k, earned value €45.0k, CPI 0.97; Workshop extension, actual cost €45.2k, earned value €51.3k, CPI 1.13; Conveyor line, actual cost €37.4k, earned value €42.0k, CPI 1.12; Electrical compliance upgrade, actual cost €37.1k, earned value €36.8k, CPI 0.99; Bottling line, actual cost €13.3k, earned value €12.8k, CPI 0.96. The HVAC renovation accounts for €184k of spending, the Bottling line €13k. The portfolio CPI, 389.2 ÷ 441.8, is 0.88: the right calculation. The simple average of the seven CPIs, which gives each project the same weight, shows 0.97: a trap.
The average of the seven CPIs shows 0.97; the portfolio actually produces €0.88 of planned work per euro spent.

The simple average gives the same weight to the HVAC project (€184k of spending) and to the Bottling line (€13k); the portfolio CPI is Σ earned value ÷ Σ actual cost.

One last view: invoicing, project by project.

Diverging bars around zero, in thousands of euros. On the left, in blue, work produced but not yet invoiced: Conveyor line €28.8k, Workshop extension €21.0k, Electrical compliance upgrade €11.2k, Quality tracking software €7.8k, for a total of €68.8k to invoice. Energy audit: 0, completed and fully invoiced. On the right, in orange, invoiced in advance: Bottling line €3.9k and HVAC renovation €26.4k, the project in trouble, for a total of €30.3k. The net total (invoiced minus produced), −€38.5k, is what a total shows: it hides these €99k of gaps.Diverging bars around zero, in thousands of euros. On the left, in blue, work produced but not yet invoiced: Conveyor line €28.8k, Workshop extension €21.0k, Electrical compliance upgrade €11.2k, Quality tracking software €7.8k, for a total of €68.8k to invoice. Energy audit: 0, completed and fully invoiced. On the right, in orange, invoiced in advance: Bottling line €3.9k and HVAC renovation €26.4k, the project in trouble, for a total of €30.3k. The net total (invoiced minus produced), −€38.5k, is what a total shows: it hides these €99k of gaps.
A net gap of −€38.5k (invoiced minus produced: €38.5k produced and not yet invoiced) hides €69k to invoice and €30k invoiced in advance.

Most of the advance invoicing sits on the project in trouble (€26.4k): its upcoming installments will bring in less than the remaining work is worth. How to account for a loss-making project is a question for your accountant; the percentage-of-completion margin on a construction job follows French GAAP.

How does your margin compare with your industry?

According to the Banque de France, France’s central bank, half of French engineering firms have an overall gross surplus ratio below 9.3%, and half of IT services companies below 7.1%. It is the margin benchmark closest to a project-based SME.

No French public statistics, however, measure budget or schedule overruns on projects. The often-quoted percentages of projects “in trouble” come from private surveys: we do not repeat any of them.

Industry (French NAF code)CompaniesOverall gross surplus ratio: Q1 · median · Q3Median DSOLabor cost per person, median
62 · Computer programming, consultancy and related activities (IT services, custom software)4,4981.9% · 7.1% · 14.9%65.6 days€76.5k
71 · Architectural and engineering activities; technical testing and analysis (engineering firms)5,4843.7% · 9.3% · 17.1%78.9 days€70.0k
73 · Advertising and market research (agencies)1,4212.2% · 6.5% · 13.7%75.7 days€71.8k
43 · Specialized construction activities (installers, finishing trades)25,6814.2% · 7.6% · 12.6%61.4 days€53.4k

The overall gross surplus ratio (“taux d’excédent brut global”) divides overall gross surplus (gross operating surplus, which is close to EBITDA, plus non-operating items) by revenue. Q1 and Q3 are the quartiles: in engineering, one company in four is below 3.7% and one in four above 17.1%. Projects sold at 18% that end at 9%, as in the example portfolio, are enough to move a firm from one quartile to another.

The median DSO in engineering, 79 days of revenue, shows why invoiced vs. produced matters: every milestone invoiced late adds to it. The DSO calculator works out yours.

Three caveats. Scope: companies subject to French corporate income tax, with revenue above €1.25 million, that filed two consecutive years of accounts. The overall gross surplus ratio is not a project margin: it is calculated after all staff costs, non-billable time included. Labor cost per person (permanent staff costs ÷ average permanent headcount) is a sanity check for your hourly rate, not a rate card.

What mistakes skew a project dashboard?

Almost every mistake in a project dashboard comes down to progress or hours: badly measured progress skews the CPI; badly costed or miscoded hours skew the margin. The eight most common:

  • Confusing budget spent with progress. 84% of the budget spent is not 84% of the work done.
  • Measuring progress with hours. The CPI then equals 1 on every project, and the dashboard stops seeing trouble coming.
  • Averaging the projects’ CPIs. 0.97 instead of 0.88 in the example.
  • Reading the monthly margin in the accounts. On fixed-price projects, it follows the invoicing schedule, not the work.
  • Costing hours at salary plus employer payroll taxes only. The margin looks comfortable, then the year ends with no profit: overhead and non-billable time were never allocated anywhere.
  • Forgetting committed purchases. Subcontracting ordered in September and invoiced in December is missing from October’s actual cost; it must go into the estimate at completion.
  • Re-forecasting the end date only at the end. Flagged three months ahead, a slip leaves time to renegotiate or add staff; flagged in the last week, it leaves only penalties.
  • Leaving hours without a project code. Booked to a “miscellaneous” code, they drop out of the projects and flatter their margins. Use a closed list of codes, plus an “internal” code for everything else.

What data should you reconcile, and how?

Price, schedule, timesheets, hourly costs, purchases and invoices already exist, in tools that don’t talk to each other. Everything hinges on one key: the project code, used everywhere, with the same breakdown into work packages.

DataWhere it livesWhat lets you match it
Price and budgetQuote, estimating spreadsheet, CRMThe project code created when the contract is signed, with the budget in hours and purchases for each work package
Schedule and progressProject management tool, project manager’s fileThe same work packages as the budget, progress entered on a fixed date
Time spentTimesheet toolThe project code and work package on every line, timesheets approved before the status date
Cost of an hourPayroll, FP&AA cost rate per person or per role, reviewed once a year
Purchases and subcontractingAccounting, purchase ordersThe project code on the purchase order and the supplier invoice, often as a cost accounting dimension (the field that allocates an accounting entry to a project)
InvoicingOrder management system, ERPThe project code on every customer invoice, with the milestone invoiced

Three decisions to write down before building

  1. The progress rule. By deliverable (0% before, 100% on acceptance), by milestone, or by the project manager’s judgment for each work package: one written rule per type of work package, the same for every project.
  2. The hourly cost rate. With overhead, margin at completion comes close to a profit figure; without it, it is a margin on direct costs. Cost accounting helps you decide.
  3. The status date. Timesheets approved, progress entered and purchases booked as of the same day, including orders placed but not yet invoiced: that is the FP&A month-end close calendar.

Excel, project management tool or Power BI: which should you choose?

For a few projects tracked by a single person, a spreadsheet is enough. Power BI becomes useful when timesheets, purchases and invoices live in three tools and have to be reconciled every month.

We sell Power BI, and many SMEs do not need it. Microsoft Project already calculates earned value; Odoo’s project dashboard shows timesheets, planned hours, milestones and, for billable projects, costs and revenues.

Your situationThe simplest optionWhy
A few projects, a single personA spreadsheetOne row per project, one update a month: an hour of work
Timesheets, purchases and invoices in the same softwareThat software’s dashboardThe data is already reconciled; add actual progress and margin at completion if it does not calculate them
The project manager tracks tasks and scheduleThe project management toolThat is what it is built for; a leadership dashboard does not replace it
Progress is not entered anywhereNo tool, yetWithout actual progress, no tool can calculate earned value
Timesheets in one tool, purchases in the accounts, invoices in the ERPPower BIA model links all three through the project code and recalculates every month
Projects, team and finance on the same pagePower BISame projects, same months, same definitions as the management dashboard

A project tracker in Excel

One row per project and ten columns: five inputs (three of them updated every month) and five calculated columns. Here is the HVAC project’s row.

ColumnInput or formulaHVAC project
A. Selling priceEntered (signed quote)€264,000
B. BudgetEntered (cost estimate)€220,000
C. Planned progressEntered (schedule)85%
D. Actual progressEntered (project manager)60%
E. Actual costEntered (hours × rate + purchases)€184,000
F. Planned valueB × C€187,000
G. Earned valueB × D€132,000
H. CPIG ÷ E0.72
I. SPIG ÷ F0.71
J. Margin at completionA − B ÷ H−€42,667

Add a total row that sums earned value and actual cost before dividing, never an average of the CPI column. The Excel dashboard guide shows how to keep the file clean. The limit is the sources: timesheets, purchases and invoices have to be copied in every month.

How much does a project dashboard cost?

In a spreadsheet or your project tool, the time it takes to build. In Power BI, the design, paid once, and the licenses, paid every month.

At Datafuji, the design is a fixed-price package of €3,000, €5,000 or €8,000 excl. VAT depending on the number of pages and sources, with an indicative lead time of 2 to 4 weeks (packages). The example report (four pages, four sources) falls under the €5,000 package; without earned value, with only timesheets and invoices, under the €3,000 one.

The author and every reader need a Power BI Pro license, at €12.10 excl. VAT per user per month, paid yearly (Power BI dashboard). For the engineering firm’s five people, author included, the first year costs 5,000 + 5 × 12.10 × 12 = €5,726 excl. VAT, licenses at French list prices. That is less than the HVAC project’s 1,033 unpaid hours, valued at €70: more than €72,000.

The lead time depends mostly on read access to timesheets, accounting and invoicing, and on a project code shared by all three.

With this dashboard, at the end of October, the HVAC project tops the list. The committee no longer discusses the month’s margin: it decides which change order to negotiate and which team to strengthen.

Frequently asked questions

What are the 3 types of dashboards?

Strategic, tactical and operational, based on Robert N. Anthony’s three levels of decision-making (1965). No standard defines this classification. An analytical dashboard, which explains a variance, is often added. In project management, we also distinguish the single-project dashboard, read every week by the project manager, from the portfolio dashboard, read every month by leadership.

What are the 5 phases of a project?

The PMBOK Guide of the Project Management Institute (PMI), in its sixth edition, organizes a project’s processes into five process groups: initiating, planning, executing, monitoring and controlling, and closing. The dashboard belongs to the fourth: it compares execution against the plan. The seventh edition (2021) is organized around twelve principles, the eighth (2025) around six principles and seven performance domains.

What is a good utilization rate?

One that covers your costs, which the hourly rate calculator works out for you: no public statistics report utilization rates by profession. Count the hours spent beyond a fixed-price budget separately: they inflate the rate without being paid for.

How do you create a project dashboard?

Start with a project code and work packages shared by timesheets, purchases and invoices, then write down a progress rule. Next, set an hourly cost rate and a monthly status date. Finally, calculate each project on its own, and the portfolio from totals.

Let’s talk about your reporting.

A 30-minute video call with Dylan Arnaud. You come away with a clear scope and a fixed price.

Dylan Arnaud, Power BI consultant and founder of Datafuji
Dylan ArnaudFounder · your single point of contact