Production dashboard: manufacturing KPIs, their formulas and a worked example

Published · Updated · 14 min read

Dylan Arnaud, founder of Datafuji

A production dashboard brings together a plant’s KPIs: OEE (overall equipment effectiveness), scrap, MTBF (mean time between failures), MTTR (mean time to restore, full downtime), unit cost, margin, inventory and OTIF (on time in full). Example: a line that was planned to run 112 hours in the week produced only 84.1 hours’ worth of good parts, for an OEE of 75.1%.

What is a production dashboard?

A production dashboard is the management tool of a manufacturing site. It brings together a dozen indicators, always calculated the same way, compared with a target or with the prior year, and updated without manual re-entry.

It does not replace the ERP (enterprise resource planning), the MES (manufacturing execution system) or the CMMS (computerized maintenance management system): it reads them and connects them. An OEE loss then also shows up in euros of unit cost and in late orders.

The SME in our example is fictitious: three lines (machining, stamping, assembly), €2.84M of revenue in October. Its figures are consistent from one indicator to the next.

Three readers, three rhythms

The same data serves three readers, each at their own pace:

ReaderWhat they readRhythm
Plant management and CFOMargin by product family, unit cost variance, inventory, OTIFEvery month, after the close
Production: operations director, shop floor supervisorsOEE by line, downtime by cause, scrap, schedule adherenceEvery day or every week
MaintenancePreventive work completed, MTBF, MTTR, equipment with the most downtimeEvery week and every month

The financial side of the plant (profit, cash, working capital requirement) belongs in the financial dashboard.

Which KPIs should a manufacturer track?

Ten KPIs cover the essentials: three for the shop floor (OEE, scrap, schedule), three for maintenance (MTBF, MTTR, preventive), three for plant economics (unit cost, margin, inventory) and one for the customer (OTIF).

A single-line site can stick to five. The source shown is the most common one; yours may differ.

KPIFormulaUsual sourceMost common pitfall
OEE (overall equipment effectiveness)Fully productive time ÷ planned production time = availability × performance × qualityMES or PLCs; ideal cycle times in the ERP routingsPublishing an OEE calculated on opening time (a TRG) as OEE.
Scrap rateScrapped parts ÷ parts producedMES, quality reports, ERP scrap transactionsCounting reworked parts as good.
Schedule adherenceConforming quantities produced ÷ planned quantities, by work orderERP (work orders), MESComparing with the latest rescheduled plan.
MTBF (mean time between failures)Run time ÷ number of failuresCMMS and MES run timeUsing calendar time instead of run time.
MTTR (mean time to restore)Total failure downtime ÷ number of failuresCMMS (start and end of work orders)Leaving out the wait for parts or a technician.
Preventive maintenance compliancePreventive work orders completed ÷ scheduledCMMSWork orders closed late.
Unit costMaterials + labor + machine time + allocated overhead, by itemERP (bills of materials, routings, work orders), cost accountingA three-year-old standard cost.
Margin by productRevenue − unit cost, by item or familyERP, accountingReading it without each family’s volume.
Days of inventoryInventory ÷ cost of sales per dayERPAdding up month-end inventories.
OTIF (on time in full)Lines delivered complete on the promised date ÷ lines dueERP (orders and shipments)Not writing down which date counts.

Where the numbers come from

The ERP holds the routings and their cycle times, the work orders, sales, inventory and costs. The MES (shop floor execution software) records machine states, parts and downtime causes; the CMMS (computerized maintenance management system) records the equipment and the work orders.

Excel almost always holds the targets and the downtime causes entered by hand. How to pull data from each ERP (SAP, Business Central, Odoo, Divalto…) is covered in Power BI and ERP.

How do you read a line’s OEE, and why not compare it with a TRG?

OEE compares the time spent making good parts with the time the line was planned to produce. In France it is called TRS and is defined by the French standard NF E60-182. French plants also publish a TRG, which divides the same time by the opening time, so it is always lower than or equal to OEE.

Opening time minus planned stops (preventive maintenance, trials, meetings) gives planned production time; minus unplanned stops (failures, changeovers, waiting), run time. Net run time is the time that all parts produced would have taken at the ideal cycle time; fully productive time, the same for good parts only.

The SME’s stamping line in week 43: 120 h of opening time, 112 h of planned production time, 14 h of unplanned stops, a 30-second cycle, 10,400 parts produced, 10,090 of them good the first time. The time cascade shows where the hours go.

Horizontal bars, on the same scale, of the stamping line’s times in week 43: 120 hours of opening time; 112 hours of planned production time, after 8 hours of planned stops; 98 hours of run time, after 14 hours of unplanned stops (availability 87.5%); 86.7 net hours, after 11.3 hours of slowdowns and minor stops (performance 88.4%); 84.1 fully productive hours, after 2.6 hours of quality losses (quality 97.0%). Losses are in orange; the largest is unplanned stops. OEE = 84.1 h ÷ 112 h = 75.1%.Horizontal bars, on the same scale, of the stamping line’s times in week 43: 120 hours of opening time; 112 hours of planned production time, after 8 hours of planned stops; 98 hours of run time, after 14 hours of unplanned stops (availability 87.5%); 86.7 net hours, after 11.3 hours of slowdowns and minor stops (performance 88.4%); 84.1 fully productive hours, after 2.6 hours of quality losses (quality 97.0%). Losses are in orange; the largest is unplanned stops. OEE = 84.1 h ÷ 112 h = 75.1%.
Out of 112 planned hours, the line produced only 84.1 hours’ worth of good parts: 27.9 hours are lost, 14 of them to unplanned stops.

The calculation, layer by layer:

Availability    = 98 h ÷ 112 h
                = 87.5%
Net run time    = 10,400 × 30 s
                = 86.7 h
Performance     = 86.7 h ÷ 98 h
                = 88.4%
Quality         = 10,090 ÷ 10,400
                = 97.0%
Productive time = 10,090 × 30 s
                = 84.1 h
OEE             = 84.1 h ÷ 112 h
                = 75.1%
TRG             = 84.1 h ÷ 120 h
                = 70.1%

Of the 27.9 hours lost, unplanned stops (14 h) weigh more than slowdowns (11.3 h) and quality losses (2.6 h): that is where the line has the most to gain.

OEE, TRG, TRE and TEEP

The French TRG (taux de rendement global, OEE on opening time) divides fully productive time by opening time; the TRE (economic) divides it by total calendar time, close to what English-speaking plants call TEEP. On the same line, TRE ≤ TRG ≤ OEE. Hence the Monday meeting where one shop reports 72% OEE, the other 64%, and the second gets the blame when it is actually reporting a TRG.

The same fully productive time, divided by two different times, gives two rates.

Two bars for the same stamping line, with the same 84.1 fully productive hours. OEE divides them by the 112 hours of planned production time: 75.1%. TRG divides them by the 120 hours of opening time, which include 8 hours of planned stops: 70.1%. The 5-point gap comes from the denominator alone. Trap: comparing one line’s OEE with another line’s TRG. Right: compare the same metric, with the same definition of planned production time.Two bars for the same stamping line, with the same 84.1 fully productive hours. OEE divides them by the 112 hours of planned production time: 75.1%. TRG divides them by the 120 hours of opening time, which include 8 hours of planned stops: 70.1%. The 5-point gap comes from the denominator alone. Trap: comparing one line’s OEE with another line’s TRG. Right: compare the same metric, with the same definition of planned production time.
Same line, same parts: 75.1% OEE, 70.1% TRG, depending on whether the 8 hours of planned stops are taken out.

The 5-point gap says nothing about the shop floor: it comes from the denominator. Before comparing two lines, ask which of the two rates each one publishes.

OEE (Overall Equipment Effectiveness) comes from Seiichi Nakajima’s TPM (Total Productive Maintenance); the international standard ISO 22400-2 also defines it. The 85% often presented as “world-class” OEE has no normative basis: it depends on the product, the batch sizes and the planned production time used.

Run the numbers on your own line

The OEE calculator uses these six inputs, starts from the stamping line’s values and puts a figure on the first loss to tackle; your numbers stay in your browser.

How do you track maintenance with MTBF, MTTR and preventive work?

Maintenance is managed with three figures taken from the CMMS. MTBF says how long a piece of equipment runs between two failures, MTTR how long it stays down. The third is the preventive maintenance compliance rate.

In October, the SME’s critical equipment ran 46 hours on average between failures, with 2.3 hours of downtime per failure. This gives its inherent availability, the part that maintenance controls:

Inherent availability
  = MTBF ÷ (MTBF + MTTR)
  = 46 ÷ (46 + 2.3)
  = 95.2%
Target: 96.8%

Press P3 pulls the average up: 9 failures for 24.3 hours of downtime, an MTTR of 2.7 hours. Under the European standard EN 13306 (French edition NF EN 13306), MTTR counts the whole stop, detection and waiting for parts included, not just the repair.

Preventive maintenance is slipping: 102 work orders completed out of 124, or 82% against a 95% target. The robots are furthest behind: 13 work orders out of 22 (59%), which nonetheless consumed 121% of the planned hours.

Actual hours above 100% mean that the task lists underestimate the time, or that work orders are being closed incorrectly. The European standard EN 15341 guides the choice of maintenance KPIs; the MTBF and MTTR calculator starts from your list of failures, pasted from a CMMS or Excel export.

How do you connect the shop floor to euros?

The shop floor translates into euros through four ERP KPIs: unit cost by item, margin by product family, days of inventory and OTIF. That is what plant management reads every month.

In October, the SME’s margin on standard cost is 24.6%, against a 26.0% target. The table by family shows where the gap comes from:

FamilyRevenue (€k)Margin (€k)Margin %TargetVariance
Machined parts1,24026021.0%24.3%−3.3 pts
Stamped parts98027428.0%28.5%−0.5 pts
Subassemblies62016526.6%25.5%+1.1 pts
Total2,84069924.6%26.0%−1.4 pts

Machined parts account for the entire gap on their own (−€41k of margin, 3.3 points on €1,240k, for a total gap of −€40k), subassemblies offset part of it, and machining is also the line with the lowest OEE in week 43 (68.9%). That is one week set against one month, with no proof that one causes the other: the dashboard is there to put the question to the right shop floor supervisor.

Inventory stands at €4.10M, €500k above the €3.60M target, including €0.62M with no movement at all in six months. Days of inventory are calculated on the month’s cost of sales (revenue minus margin: 2.84 − 0.70 = €2.14M), divided by 31 days:

Days of inventory = €4,100k
                  ÷ (€2,140k ÷ 31 d)
                  = 59 days
Target: 51 days

The 8-day gap is worth about €550k (2,140 ÷ 31 × 8), not €500k: the two targets do not use the same basis, so write down which one counts.

Finally, OTIF stands at 91.5% against a 95% target; OTD (on-time delivery) looks only at the date, not the quantities. OTIF is only meaningful if the reference date is written down: depending on the date used, requested or confirmed, and the tolerance, the gap can reach several points (OTIF calculator).

What do a plant’s dashboards look like?

A plant reads three reports built on the same data: site management, production and maintenance. Each fits on two pages and answers one question per page.

The summary page of the site management report fits on one screen.

Screenshot of the “Site management” Power BI report, Summary page, October: revenue €2.84M (−3.7% against €2.95M), margin on standard cost 24.6% (−1.4 points against 26.0%), OTIF 91.5% (−3.5 points against 95.0%), OTIF line chart from January to October and a table of margin by product family.Screenshot of the “Site management” Power BI report, Summary page, October: revenue €2.84M (−3.7% against €2.95M), margin on standard cost 24.6% (−1.4 points against 26.0%), OTIF 91.5% (−3.5 points against 95.0%), OTIF line chart from January to October and a table of margin by product family.
Three figures compared with their target, the OTIF trend and margin by family: management reads its month on one page.
ReportPages and questionHeadline KPIs (example SME)SourcesRefresh
Site managementIs the site hitting its targets this month? Where is inventory above target?Revenue €2.84M; margin 24.6%; OTIF 91.5%; inventory €4.10M; 59 days of inventoryERP, cost accounting, Excel targetsEvery night; final after the close
ProductionIs the site hitting its OEE target? Where are we losing hours to downtime?OEE 71.8%; availability 86.2%; performance 87.0%; 46 h of downtime; scrap 3.1%MES or shop floor entries, ERP (schedule and routings)Several times a day or every night
MaintenanceIs critical equipment failing less often? Where is preventive maintenance slipping?MTBF 46 h; MTTR 2.3 h; preventive 82%; corrective 38% of hoursCMMS, MES run timeEvery night

The “downtime” page of the production report triggers the most action; a Pareto chart of causes (sorted from largest to smallest) is enough to read it.

Horizontal bars of unplanned stops in week 43, sorted by duration, 46 hours in total: mechanical failure 14 h, changeover 10 h, waiting for material 8 h, adjustment 6 h, cause not entered 5 h, electrical failure 3 h. The top two causes account for 24 of the 46 hours, or 52%. The “cause not entered” bar, in orange, represents 11% of hours with no known cause.Horizontal bars of unplanned stops in week 43, sorted by duration, 46 hours in total: mechanical failure 14 h, changeover 10 h, waiting for material 8 h, adjustment 6 h, cause not entered 5 h, electrical failure 3 h. The top two causes account for 24 of the 46 hours, or 52%. The “cause not entered” bar, in orange, represents 11% of hours with no known cause.
Mechanical failures and changeovers make up more than half of the 46 hours of downtime; 5 hours have no cause at all.

The top two causes account for 24 of the 46 hours, or 52%; changeovers can be shortened with the SMED method (single-minute exchange of die, a changeover in under ten minutes). A second Pareto, by number of stops, tells you whether a cause matters because of a few long failures or many short stops. Other functions have their own typical report in the Power BI dashboard guide.

Which mistakes skew manufacturing KPIs?

Plant KPIs are skewed mostly by definitions that vary from one site to another, averages of percentages, incomplete machine data and equipment that does not carry the same code everywhere.

An OEE that does not mean the same thing from one site to another

At 64% against 72%, the second site is not necessarily worse. Beyond OEE versus TRG, four choices move the figure:

  • The ideal cycle time. With the cycle time from the quote, slower than the machine builder’s, performance is artificially inflated.
  • Changeovers. Planned stops at one site, they fall outside planned production time; unplanned at the other, they weigh on availability.
  • Minor stops. Recorded as stops here, elsewhere they end up in the performance gap: OEE does not change, the cause shown does.
  • Rework. Counted as good, it inflates quality. Count only parts that are good the first time: at the SME’s site, scrap is 3.1%, but OEE quality is 95.7%, rework excluded.

The remedy: a written definition, the same everywhere, applied in the data model.

Averaging OEE

A site’s OEE is not the average of its lines’ OEE. Line A, planned for 100 hours at 80%, and line B, planned for 20 hours at 50%, give 65% as a simple average. Instead, add up the fully productive times and the planned production times, then divide:

Site OEE = (80 h + 10 h)
         ÷ (100 h + 20 h)
         = 75%   (not 65%)

The same rule applies to the days of the week, MTBF, MTTR and the scrap rate. Inventory, on the other hand, does not add up over time: the quarter’s inventory is the one at the end of the period.

Incomplete machine data

A PLC’s part counter is reliable; the cause of a stop is often entered by hand, after the fact, or not at all. Show the share of “cause not entered” and track it as an indicator, instead of filing it under “Other.”

The other classic gap is a piece of equipment that goes by a different name in each system.

Three records for the same press: “P3” in the MES, with machine states and stops by cause; “PRS-003” in the CMMS, with 9 failures in October, 24.3 hours of downtime and an MTTR of 2.7 hours; “400 t press” in the supervisor’s Excel file, with stop causes entered by hand. Without a table, there is no link between the failure and OEE. Below, a four-column mapping table, Equipment, MES, CMMS and Excel, in which a single row links the three codes: 400 t press, P3, PRS-003, 400 t press.Three records for the same press: “P3” in the MES, with machine states and stops by cause; “PRS-003” in the CMMS, with 9 failures in October, 24.3 hours of downtime and an MTTR of 2.7 hours; “400 t press” in the supervisor’s Excel file, with stop causes entered by hand. Without a table, there is no link between the failure and OEE. Below, a four-column mapping table, Equipment, MES, CMMS and Excel, in which a single row links the three codes: 400 t press, P3, PRS-003, 400 t press.
One row in a mapping table is enough to link a failure in the CMMS to an OEE loss in the MES.

Without this table, there is no way to tell how much the press costs in OEE. Other frequent gaps: clocks out of sync, stops straddling two shifts, work orders closed late that skew MTTR.

Which public benchmarks can a manufacturing SME compare itself with?

For French industry, the Banque de France (the French central bank), INSEE (the French national statistics office) and the Assurance Maladie (French national health insurance, which covers workplace accidents) publish benchmarks: payment terms, inventory levels, profit share, hourly labor cost, accident rates. No public statistic gives a reference OEE.

Collected on November 20, 2026, these French figures help situate a company without setting it a target; check the scope of each one, manufacturing or industry in the broad sense:

IndicatorBenchmark for industryYear and scopeSource
Customer payment terms (DSO)Manufacturing: 43.9 days of revenue on average; 41.5 across all sectors2025, excluding micro-enterprises, on a 360-day basisBanque de France
Supplier payment terms (DPO)50.9 days of purchases2025, same scopeBanque de France
Net trade credit (receivables minus payables)12.2 days of revenue2025, same scopeBanque de France
Inventory levelMedian 43.1 days of revenue excl. VAT; a quarter below 18.3, a quarter above 81.32024, companies with revenue above €1.25M, on a 360-day basisBanque de France, sector report
Profit share (gross operating surplus ÷ value added)Median 22.2%2024, same scopeBanque de France, sector report
Value added rate23.9% in industry (excluding construction)2023, non-farm, non-financial market sectorsINSEE
Hourly labor cost€47.70 in industry (excluding construction), €44.70 across all market sectors (B to N)2025, companies with 10 or more employeesINSEE and Eurostat
Capacity utilization rate82%, against an average of 83% since 1976July 2026, business surveyINSEE
Workplace accidentsFrequency index of 24.5 per 1,000 employees (25.2 in 2023)2024, general social security schemeAssurance Maladie

Four precautions before using them:

  • Redo the calculation with the source’s formula. The Banque de France calculates on 360 days and divides inventory by revenue excl. VAT, not by cost of sales.
  • An average is not a median. The 43.9-day customer payment term is an average; the sector report’s median, 49.8 days, covers a different population.
  • Drill down to your NAF code (INSEE’s French activity code, comparable to a NAICS code) when it exists: for accidents, industrial machining (2562B) has a frequency index of 29.4 per 1,000 employees. This French index counts accidents per 1,000 employees, not per hours worked like the LTIFR or the US OSHA rates (LTIFR calculator); the sector reports also break down by division (financial ratios).
  • For OEE, OTIF, MTBF or scrap, the benchmark is your own history, line by line.

The first precaution changes everything for the SME’s inventory.

Two calculations of the same €4,100k inventory. Internal days of cover: €4,100k divided by €2,140k of cost of sales spread over 31 days, or 59 days, 8 days above the 51-day target. Inventory in days of revenue as defined by the Banque de France (French central bank): €4,100k divided by €34,080k of annualized revenue excl. VAT (October × 12), multiplied by 360, or 43 days. On a 0 to 90-day scale, half of French manufacturing companies fall between 18.3 and 81.3 days in 2024, with a median of 43.1 days: the Banque de France calculation lands on the median. Trap: comparing 59 days with a median calculated another way. Right: redo the calculation with the source’s formula.Two calculations of the same €4,100k inventory. Internal days of cover: €4,100k divided by €2,140k of cost of sales spread over 31 days, or 59 days, 8 days above the 51-day target. Inventory in days of revenue as defined by the Banque de France (French central bank): €4,100k divided by €34,080k of annualized revenue excl. VAT (October × 12), multiplied by 360, or 43 days. On a 0 to 90-day scale, half of French manufacturing companies fall between 18.3 and 81.3 days in 2024, with a median of 43.1 days: the Banque de France calculation lands on the median. Trap: comparing 59 days with a median calculated another way. Right: redo the calculation with the source’s formula.
The same inventory is 59 days of internal cover, but 43 days as the Banque de France measures it.

The Banque de France calculation assumes annual revenue of 2.84 × 12 = €34.1M, a simplification. That does not make the SME “average”: it is managed against its own 51-day target.

How do you set up a production dashboard?

A production dashboard is set up in five steps. You write the definition of each KPI and list its source. Then you share one list of equipment, build the pages by reader, and reconcile the figures over past weeks.

  1. Write each definition, starting with what OEE’s planned production time includes and which date counts for OTIF.
  2. List the source of each figure: MES, ERP, CMMS or Excel, with the person who maintains it.
  3. Share one equipment list between the MES and the CMMS: the mapping table for press P3.
  4. Build the pages by reader: plant management, production, maintenance.
  5. Reconcile the figures over a few past weeks before retiring the old tracking.

Do you need Power BI, or is your MES enough?

Power BI is for bringing several sources together to analyze by shift, by day, by site. If a single tool already sees everything you manage, its reports are often enough.

Your situationThe simplest optionWhy
An MES in place covers OEE, downtime and scrapThe MES dashboardsThey are wired as close to the machines as possible.
A real-time shop floor screen, machine by machineThe MES or OEE tracking softwarePower BI is for analysis, not second-by-second display.
No machine data: everything is on paperCapture the data firstTablets, counting devices or an MES: a dashboard does not create data.
Only maintenance reads its indicatorsThe CMMS reportsCheck first what it can do on its own.
One line, one supervisor, one sheet kept every dayA spreadsheetIt is enough as long as it does not circulate in several versions.
ERP, MES, CMMS and Excel targets on the same pagePower BIIt links an OEE loss to its cost and its delays.
Several sites to comparePower BIOne OEE definition for all, permissions by reader.

For maintenance, the CMMS already contains the essentials. What remains is to write down when a work order counts as done, group the machines by line, and keep queries the team can read.

What a production dashboard costs

Two cost items: the design, paid once, and the licenses. A production report on its own (MES and a targets file) costs €3,000 excl. VAT as a fixed-price package. The three reports together (six pages, ERP, MES, CMMS and Excel) cost €5,000 excl. VAT (package details).

To share a report, the author and every reader need a Power BI Pro license, at €12.10 excl. VAT per user per month (annual billing, French list price). For eight users:

Licenses = 8 users
         × €12.10 × 12 months
         = €1,161.60/year excl. VAT,
           at French list prices

The lead time, 2 to 4 weeks, depends mainly on your read access and your definitions.

In the end, the Monday meeting no longer compares an OEE with a TRG. It sees that mechanical failures lead in week 43, that press P3 racked up 24.3 hours of failures in October, and decides who brings its preventive maintenance forward, and when.

Frequently asked questions

What is manufacturing performance?

It is a plant’s ability to deliver what was ordered, on the promised date, at the expected quality and cost. It is measured on four fronts: equipment effectiveness (OEE), quality (scrap), service (OTIF) and cost. Any one of them alone is misleading: an OEE inflated by long production runs drives inventory up.

What are the main production KPIs?

OEE and its three components (availability, performance, quality), scrap rate, schedule adherence, MTBF and MTTR. On the plant economics side, add unit cost, margin, inventory and OTIF. A single line can start with OEE, scrap and downtime by cause.

What are the 3 types of KPIs?

A common classification separates outcome indicators (OEE, margin, OTIF), activity or process indicators (preventive maintenance completed, schedule met) and alert indicators (scrap above a threshold, inventory beyond its target days of cover). A plant dashboard mixes all three.

What are the quality KPIs in production?

Scrap rate divides scrapped parts by parts produced; first-pass yield is the share of parts that conform without rework. Add defects in PPM (nonconforming parts per million) and the cost of poor quality, in euros. On the customer side, add the complaint rate.

Can you build a production dashboard in Excel?

Yes, as long as there are one or two sources and a weekly update: an entry sheet per shift, a targets table, and formulas that add up times before dividing. Excel reaches its limit when you need to combine MES, CMMS and ERP data every day, or compare several plants.

Let’s talk about your reporting.

A 30-minute video call with Dylan Arnaud. You come away with a clear scope and a fixed price.

Dylan Arnaud, Power BI consultant and founder of Datafuji
Dylan ArnaudFounder · your single point of contact