title: "Project dashboard: 10 KPIs, earned value, example | Datafuji"
url: "https://www.datafuji.com/en/project-dashboard"
lang: en
updated: 2026-11-28
agent:
  instructions: "Use this search API to find relevant content across this site with keywords or natural-language queries, instead of crawling individual pages. Results are returned in Markdown."
  endpoint: "https://www.datafuji.com/.well-known/search?q={query}"
  method: "GET"
  documentation: "https://developers.cloudflare.com/ai-search/how-to/search-for-agents/"
---

- [Home](https://www.datafuji.com/en)

- Project dashboard

# Project dashboard: 10 KPIs, earned value and a portfolio example

Published November 28, 2026 · Updated November 28, 2026 · 15 min read

[Dylan Arnaud](https://www.datafuji.com/en/about#dylan-arnaud), founder of Datafuji

A project dashboard shows, for each active project, what was planned, what has been done and what has been spent, and from these derives the likely margin and end date. Example: a project budgeted at €220,000 that is 60% complete after €184,000 of spending will cost about €307,000 at this rate.

## What is a project dashboard?

A project dashboard tells you whether each project will finish within its price and by what date, early enough to act. It reconciles four sources: the schedule, timesheets, purchases and invoicing.

It is built for businesses that sell project work: engineering firms, IT services companies, agencies, installers. Their profit is the sum of their project margins, and a single overrun can wipe it out. Construction jobs have their own rules (progress billing, retainage), covered in our [construction](https://www.datafuji.com/en/industries/construction) guide.

### Single-project or portfolio dashboard

Same data, different reader, different cadence; project reporting, by contrast, keeps stakeholders informed rather than steering the project.

| | Single-project dashboard | Portfolio dashboard | Project reporting |
| --- | --- | --- | --- |
| Reader | The project manager | Leadership | The client, the steering committee |
| Frequency | Every week | Every month | At each milestone or committee meeting |
| Content | Tasks, milestones, risks, hours per person | One row per project: margin at completion, slippage, invoiced | Progress, deliverables, risks, decisions needed |
| Question | What do we do this week? | Where do we step in this month? | Where do we stand? |

The portfolio view is the one SMEs most often lack: project management tools show each project well, but rarely the whole portfolio in euros. A “green, amber, red” status self-reported by the project manager belongs in reporting; on the dashboard, the color has to come from a calculation.

## Which KPIs should a project dashboard track?

Ten project metrics are enough for an SME: will we make money (1 to 5), will we finish on time (6), what price are we getting for our time (7, 8), and are we invoicing what we produce (9, 10)?

| KPI | Formula | Data source | Pitfall |
| --- | --- | --- | --- |
| 1. Margin at completion | Selling price − estimate at completion (EAC, what the project will have cost at the end). As a %: ÷ selling price | Signed quote, budget, timesheets, allocated purchases | Tracking the monthly margin in the accounting books: on a half-finished fixed-price project, it tells you nothing. |
| 2. Cost performance index (CPI) | Earned value (work done, in budget euros) ÷ actual cost | Budget, progress, timesheets and purchases | Assuming progress equals budget spent: the CPI then always comes out at 1. |
| 3. Schedule performance index (SPI) | Earned value ÷ planned value | Baseline schedule, actual progress | Reading it as a delay in days: it measures euros of work and returns to 1 at the end of the project. |
| 4. Actual progress and budget spent | Progress measured on deliverables, compared with actual cost ÷ budget | Project manager, timesheets | Estimating it “by feel”; instead, count 0% until a work package has started and 100% once it is accepted. |
| 5. Estimate to complete | EAC − actual cost; in hours: hours at completion − hours spent | Calculation, checked by the project manager | Confusing it with budget − spent, which is only what is left of the budget. |
| 6. Schedule slippage | Forecast end date − contractual end date, in weeks | Schedule, project manager | Re-forecasting the end date only at the end of the project. |
| 7. Realized day rate | Fixed price ÷ days at completion, estimated as days spent ÷ actual progress | Quote, timesheets | Comparing it with the sold day rate without looking at what a day actually costs. |
| 8. [Utilization rate](https://www.datafuji.com/en/kpi#kpi-taux-occupation) | Billable hours ÷ available hours | Schedule, timesheets | Aiming for 100%. Training, presales and vacation are real: define what counts as available hours, and set a realistic target for each role. |
| 9. Invoiced vs. produced | Invoiced to date − price × actual progress, project by project | Invoicing, progress | Looking only at the total: a project invoiced in advance hides one that has not been invoiced yet. |
| 10. [Order backlog](https://www.datafuji.com/en/kpi#kpi-carnet-de-commandes) | Signed orders not yet invoiced. In months: backlog ÷ average monthly revenue | Order management system or ERP | Leaving in orders with no delivery date or put on hold by the client: the backlog looks full, yet none of it will be invoiced this quarter. |

An SME just getting started can stick to KPIs 1, 4, 6 and 9. All they need is a budget per project, progress entered every month, timesheets and invoices; the others can be derived from them.

### The realized day rate: what a day is really worth

On a fixed-price project, the price is fixed; the number of days is not. The “Quality tracking software” project in the example portfolio below has no purchases and is sold for €156,000 for 257 budgeted days: a sold day rate of €607.

It is 55% complete after 1,120 hours; at the same pace, it will take 2,036, and the realized day rate will fall to €536. With a day costing €490 (€70 × 7 hours), the margin drops from 19.2% to 8.6% of the price. The [hourly rate calculator](https://www.datafuji.com/en/tools/hourly-rate-calculator#day-rate) walks through the step from sold day rate to realized day rate.

## How do you measure progress in euros? Earned value

Earned value management (EVM) converts progress into euros, so it can be compared with what has been spent and what was planned. Below 1, either of its two indices signals that the project is drifting.

It is described in the ISO 21508 standard and in U.S. government guides; Microsoft Project calls earned value the “budgeted cost of work performed” (BCWP).

### Three values, as of the same date

- Planned value (PV): the share of the budget for the work that should have been done by this date. Budget × planned progress.

- Earned value (EV): the share of the budget for the work actually done. Budget × actual progress.

- Actual cost (AC): what was spent to do this work. Hours spent × hourly cost rate, plus purchases and subcontracting.

The budget (BAC, budget at completion) is the cost estimated when the job was priced, not the selling price: the difference between the two is the planned margin.

The running example is the “HVAC renovation” project (heating, ventilation and air conditioning) of a fictional engineering firm. Sold for €264,000 excl. VAT, it is budgeted at 2,800 hours and €24,000 of purchases. Hours are costed at €70, the cost rate from the [hourly rate calculator](https://www.datafuji.com/en/tools/hourly-rate-calculator) example, overhead included.

As of October 31, the schedule called for 85% completion; the project manager reports 60%, after 2,300 hours and €23,000 of purchases. Yet the books show a healthy margin for the month: without this reconciliation, the loss would only surface in February, too late to act.

![Three bars on a scale from 0 to €220,000, the HVAC renovation project’s budget, as of October 31. Planned value: €187,000, 85% of the budget, what should have been done. Earned value: €132,000, 60%, what has been done. Actual cost: €184,000, 84% of the budget, what has been spent; its bar almost reaches the end of the planned value bar. Between earned value and planned value, the schedule variance of −€55,000 (SPI 0.71); between earned value and actual cost, the cost variance of −€52,000 (CPI 0.72). At the bottom, 84% of the budget spent, a wrong reading if taken as progress, against actual progress of 60%, measured on deliverables.](https://www.datafuji.com/img/en/tableau-de-bord-projet/tableau-de-bord-projet-01.svg)

*84% of the budget spent for 60% of the work done: actual cost has almost caught up with planned value.*

### The formulas, applied to the HVAC project

Budget (BAC) = 2,800 h × €70 + €24,000 = €220,000 Planned value = 220,000 × 85% = €187,000 Earned value = 220,000 × 60% = €132,000 Actual cost = 2,300 h × €70 + €23,000 = €184,000 CPI = 132,000 ÷ 184,000 = 0.72 SPI = 132,000 ÷ 187,000 = 0.71 EAC = 220,000 ÷ 0.72 = €306,667 Margin at completion = 264,000 − 306,667 = −€42,667

Every euro spent has produced €0.72 worth of planned work, and 71% of the work expected by this date has been done. The table completes the picture:

| Metric | Formula | HVAC project | What it means |
| --- | --- | --- | --- |
| Cost variance (CV) | EV − AC | −€52,000 | The work done cost more than planned |
| Schedule variance (SV) | EV − PV | −€55,000 | Less work done than planned, in euros |
| Estimate to complete (ETC) | EAC − AC | €122,667 | What still has to be spent |
| Variance at completion (VAC) | BAC − EAC | −€86,667 | The expected overrun |
| Margin at completion | Price − EAC | −€42,667, or −16.2% | Sold at a 16.7% margin, it will end at a loss |

The indices are read against 1. The U.S. Department of Energy guide sums it up in one line: “Favorable is >1.0, unfavorable is <1.0.”

### Which EAC formula should you use?

They all rest on the same idea: actual cost + remaining work ÷ an efficiency index. The cost guide of the GAO (U.S. Government Accountability Office) recommends calculating several and looking at the spread.

| Assumption about the rest of the project | Formula | Estimate |
| --- | --- | --- |
| The remaining work is done at the planned cost | AC + (BAC − EV) | €272,000 |
| The remaining work is done at the efficiency observed so far | BAC ÷ CPI, or AC + (BAC − EV) ÷ CPI | €306,667 |
| The delay costs money too | AC + (BAC − EV) ÷ (CPI × SPI) | €357,778 |

We use budget ÷ CPI, which the Department of Energy labels the “general” formula, and show the composite formula (CPI × SPI, third row) alongside it when it is higher. The “planned cost” formula assumes the project will suddenly start holding to its budget, and nothing points to that.

According to the GAO, among the formulas that use an index, the cumulative CPI (calculated from the start of the project) generally gives the lowest estimate, and CPI × SPI the worst case. Once a project is 20% complete, the cumulative CPI varies by less than 10%, and it most often gets worse from there.

![Cost scale from €200,000 to €370,000 for the HVAC renovation project. Markers: budget €220,000 and selling price €264,000; beyond the price, the project loses money. The three estimates at completion are all beyond the price. If the rest is done at planned cost, AC + (BAC − EV): €272,000, an €8,000 loss. At the efficiency observed so far, BAC ÷ CPI, the estimate used: €306,667, a €42,667 loss. If the delay costs money too, AC + (BAC − EV) ÷ (CPI × SPI): €357,778, a €93,778 loss. The most likely range runs from €306,667 to €357,778.](https://www.datafuji.com/img/en/tableau-de-bord-projet/tableau-de-bord-projet-02.svg)

*Even if the rest of the project is done at planned cost, the HVAC renovation will cost €272,000 against a price of €264,000.*

The question is no longer whether the project will lose money, but how much: between €8,000 and €94,000, more likely at the high end of the range.

### What earned value does not tell you

- It is only as good as the progress measure. Measure progress on deliverables, one work package at a time; derived from hours spent, it produces a CPI that always equals 1.

- The SPI measures a delay in euros, not in days. It returns to 1 at the end of the project, even a very late one: the GAO notes that it loses its predictive value. Track the forecast end date alongside it.

- Before 20% completion, do not draw conclusions. The “Bottling line” project in the example portfolio below has a CPI of 0.96 at 8% completion: a signal to watch, not a verdict.

- On time-and-materials work, it says nothing about margin. Every hour is billed: track the budget the client approved and the date you will reach it.

- It is blind to quality. A work package redone three times shows up in actual cost, not in progress, provided the rework is booked to the project.

## What does a project portfolio dashboard look like?

A portfolio dashboard fits on four pages: will the portfolio hold its margin, which projects are slipping, is the team busy enough, and are we invoicing what we produce? One row per project, calculated totals.

The example is a fictional 5-person engineering firm: 7 fixed-price projects, €996k in combined selling price, status as of October 31, made-up data, calculated metrics.

![Screenshot of the “Portfolio” page of a fictional Power BI report. Three cards: margin at completion €88k (8.8% of price, plan €179k), CPI 0.88, SPI 0.84. On the left, work done by month (price × progress) and its variance to plan; on the right, each project’s planned margin and margin at completion, including HVAC at −€42.7k.](https://www.datafuji.com/img/en/tableau-de-bord-projet/exemple-clair.webp)

*The portfolio was expected to earn €179k in margin; at the current pace, it will earn €88k.*

Only one row goes negative. The seven projects in detail:

| Project | Price | CPI | SPI | Planned margin | Margin at completion | Slippage |
| --- | --- | --- | --- | --- | --- | --- |
| Conveyor line | €72k | 1.12 | 1.17 | 16.7% | 25.8% | 1 week ahead |
| HVAC renovation | €264k | 0.72 | 0.71 | 16.7% | −16.2% | +13 weeks |
| Quality tracking software | €156k | 0.88 | 1.10 | 19.2% | 8.6% | 0 |
| Workshop extension | €140k | 1.13 | 0.64 | 18.6% | 28.3% | +8 weeks |
| Electrical compliance upgrade | €112k | 0.99 | 1.00 | 17.9% | 17.2% | 0 |
| Energy audit (completed) | €56k | 0.97 | 1.00 | 19.6% | 17.1% | +1 week |
| Bottling line | €196k | 0.96 | 0.80 | 18.4% | 15.2% | 0 |
| Portfolio | €996k | 0.88 | 0.84 | 18.0% | 8.8% | n/a |

### What this report reveals in two minutes

One project explains almost everything. The HVAC renovation alone accounts for €86.7k of the €91.5k of margin the portfolio will lose (€179k planned, €87.5k at completion), or 95%. The CEO sees it at the end of October, 4 weeks before the contractual end date, not after.

A good CPI can hide a delay. The Workshop extension is spending less than planned (CPI 1.13) because it is progressing slowly (SPI 0.64): the client’s data is late, and the end date slips by 8 weeks. That is not a saving; it is revenue being pushed back.

The project running ahead calls for action. The Conveyor line (CPI 1.12, SPI 1.17) sees its margin rise to 25.8%, against 16.7% planned. With 70% of the work produced and 30% invoiced, it has €28.8k of invoices waiting to go out.

A utilization rate on target can hide lost hours. The team is at 76.1% against a 76.0% target (71.9% a year earlier). But the HVAC project has used 2,300 hours for 60% progress: at that pace, it will take 3,833 hours for the 2,800 sold. The 1,033 hours the client will not pay for still count as billable.

Portfolio metrics are calculated from totals, never by averaging project-level figures.

![Seven projects, each with a bar scaled to its actual cost (outline) and its earned value (solid), in thousands of euros, and its CPI: HVAC renovation, actual cost €184.0k, earned value €132.0k, CPI 0.72; Quality tracking software, actual cost €78.4k, earned value €69.3k, CPI 0.88; Energy audit, actual cost €46.4k, earned value €45.0k, CPI 0.97; Workshop extension, actual cost €45.2k, earned value €51.3k, CPI 1.13; Conveyor line, actual cost €37.4k, earned value €42.0k, CPI 1.12; Electrical compliance upgrade, actual cost €37.1k, earned value €36.8k, CPI 0.99; Bottling line, actual cost €13.3k, earned value €12.8k, CPI 0.96. The HVAC renovation accounts for €184k of spending, the Bottling line €13k. The portfolio CPI, 389.2 ÷ 441.8, is 0.88: the right calculation. The simple average of the seven CPIs, which gives each project the same weight, shows 0.97: a trap.](https://www.datafuji.com/img/en/tableau-de-bord-projet/tableau-de-bord-projet-04.svg)

*The average of the seven CPIs shows 0.97; the portfolio actually produces €0.88 of planned work per euro spent.*

The simple average gives the same weight to the HVAC project (€184k of spending) and to the Bottling line (€13k); the portfolio CPI is Σ earned value ÷ Σ actual cost.

One last view: invoicing, project by project.

![Diverging bars around zero, in thousands of euros. On the left, in blue, work produced but not yet invoiced: Conveyor line €28.8k, Workshop extension €21.0k, Electrical compliance upgrade €11.2k, Quality tracking software €7.8k, for a total of €68.8k to invoice. Energy audit: 0, completed and fully invoiced. On the right, in orange, invoiced in advance: Bottling line €3.9k and HVAC renovation €26.4k, the project in trouble, for a total of €30.3k. The net total (invoiced minus produced), −€38.5k, is what a total shows: it hides these €99k of gaps.](https://www.datafuji.com/img/en/tableau-de-bord-projet/tableau-de-bord-projet-05.svg)

*A net gap of −€38.5k (invoiced minus produced: €38.5k produced and not yet invoiced) hides €69k to invoice and €30k invoiced in advance.*

Most of the advance invoicing sits on the project in trouble (€26.4k): its upcoming installments will bring in less than the remaining work is worth. How to account for a loss-making project is a question for your accountant; the [percentage-of-completion margin on a construction job](https://www.datafuji.com/en/industries/construction#margin) follows French GAAP.

## How does your margin compare with your industry?

According to the Banque de France, France’s central bank, half of French engineering firms have an overall gross surplus ratio below 9.3%, and half of IT services companies below 7.1%. It is the margin benchmark closest to a project-based SME.

No French public statistics, however, measure budget or schedule overruns on projects. The often-quoted percentages of projects “in trouble” come from private surveys: we do not repeat any of them.

| Industry (French NAF code) | Companies | Overall gross surplus ratio: Q1 · median · Q3 | Median DSO | Labor cost per person, median |
| --- | --- | --- | --- | --- |
| 62 · Computer programming, consultancy and related activities (IT services, custom software) | 4,498 | 1.9% · 7.1% · 14.9% | 65.6 days | €76.5k |
| 71 · Architectural and engineering activities; technical testing and analysis (engineering firms) | 5,484 | 3.7% · 9.3% · 17.1% | 78.9 days | €70.0k |
| 73 · Advertising and market research (agencies) | 1,421 | 2.2% · 6.5% · 13.7% | 75.7 days | €71.8k |
| 43 · Specialized construction activities (installers, finishing trades) | 25,681 | 4.2% · 7.6% · 12.6% | 61.4 days | €53.4k |

The overall gross surplus ratio (“taux d’excédent brut global”) divides overall gross surplus (gross operating surplus, which is close to EBITDA, plus non-operating items) by revenue. Q1 and Q3 are the quartiles: in engineering, one company in four is below 3.7% and one in four above 17.1%. Projects sold at 18% that end at 9%, as in the example portfolio, are enough to move a firm from one quartile to another.

The median DSO in engineering, 79 days of revenue, shows why invoiced vs. produced matters: every milestone invoiced late adds to it. The [DSO calculator](https://www.datafuji.com/en/tools/dso-calculator) works out yours.

Three caveats. Scope: companies subject to French corporate income tax, with revenue above €1.25 million, that filed two consecutive years of accounts. The overall gross surplus ratio is not a project margin: it is calculated after all staff costs, non-billable time included. Labor cost per person (permanent staff costs ÷ average permanent headcount) is a sanity check for your hourly rate, not a rate card.

## What mistakes skew a project dashboard?

Almost every mistake in a project dashboard comes down to progress or hours: badly measured progress skews the CPI; badly costed or miscoded hours skew the margin. The eight most common:

- Confusing budget spent with progress. 84% of the budget spent is not 84% of the work done.

- Measuring progress with hours. The CPI then equals 1 on every project, and the dashboard stops seeing trouble coming.

- Averaging the projects’ CPIs. 0.97 instead of 0.88 in the example.

- Reading the monthly margin in the accounts. On fixed-price projects, it follows the invoicing schedule, not the work.

- Costing hours at salary plus employer payroll taxes only. The margin looks comfortable, then the year ends with no profit: overhead and non-billable time were never allocated anywhere.

- Forgetting committed purchases. Subcontracting ordered in September and invoiced in December is missing from October’s actual cost; it must go into the estimate at completion.

- Re-forecasting the end date only at the end. Flagged three months ahead, a slip leaves time to renegotiate or add staff; flagged in the last week, it leaves only penalties.

- Leaving hours without a project code. Booked to a “miscellaneous” code, they drop out of the projects and flatter their margins. Use a closed list of codes, plus an “internal” code for everything else.

## What data should you reconcile, and how?

Price, schedule, timesheets, hourly costs, purchases and invoices already exist, in tools that don’t talk to each other. Everything hinges on one key: the project code, used everywhere, with the same breakdown into work packages.

| Data | Where it lives | What lets you match it |
| --- | --- | --- |
| Price and budget | Quote, estimating spreadsheet, CRM | The project code created when the contract is signed, with the budget in hours and purchases for each work package |
| Schedule and progress | Project management tool, project manager’s file | The same work packages as the budget, progress entered on a fixed date |
| Time spent | Timesheet tool | The project code and work package on every line, timesheets approved before the status date |
| Cost of an hour | Payroll, FP&A | A cost rate per person or per role, reviewed once a year |
| Purchases and subcontracting | Accounting, purchase orders | The project code on the purchase order and the supplier invoice, often as a cost accounting dimension (the field that allocates an accounting entry to a project) |
| Invoicing | Order management system, ERP | The project code on every customer invoice, with the milestone invoiced |

### Three decisions to write down before building

- The progress rule. By deliverable (0% before, 100% on acceptance), by milestone, or by the project manager’s judgment for each work package: one written rule per type of work package, the same for every project.

- The hourly cost rate. With overhead, margin at completion comes close to a profit figure; without it, it is a margin on direct costs. [Cost accounting](https://www.datafuji.com/en/cost-accounting) helps you decide.

- The status date. Timesheets approved, progress entered and purchases booked as of the same day, including orders placed but not yet invoiced: that is the FP&A [month-end close calendar](https://www.datafuji.com/en/fp-and-a#month-end-close).

## Excel, project management tool or Power BI: which should you choose?

For a few projects tracked by a single person, a spreadsheet is enough. Power BI becomes useful when timesheets, purchases and invoices live in three tools and have to be reconciled every month.

We sell Power BI, and many SMEs do not need it. Microsoft Project already calculates earned value; Odoo’s project dashboard shows timesheets, planned hours, milestones and, for billable projects, costs and revenues.

| Your situation | The simplest option | Why |
| --- | --- | --- |
| A few projects, a single person | A spreadsheet | One row per project, one update a month: an hour of work |
| Timesheets, purchases and invoices in the same software | That software’s dashboard | The data is already reconciled; add actual progress and margin at completion if it does not calculate them |
| The project manager tracks tasks and schedule | The project management tool | That is what it is built for; a leadership dashboard does not replace it |
| Progress is not entered anywhere | No tool, yet | Without actual progress, no tool can calculate earned value |
| Timesheets in one tool, purchases in the accounts, invoices in the ERP | Power BI | A model links all three through the project code and recalculates every month |
| Projects, team and finance on the same page | Power BI | Same projects, same months, same definitions as the [management dashboard](https://www.datafuji.com/en/management-dashboard) |

### A project tracker in Excel

One row per project and ten columns: five inputs (three of them updated every month) and five calculated columns. Here is the HVAC project’s row.

| Column | Input or formula | HVAC project |
| --- | --- | --- |
| A. Selling price | Entered (signed quote) | €264,000 |
| B. Budget | Entered (cost estimate) | €220,000 |
| C. Planned progress | Entered (schedule) | 85% |
| D. Actual progress | Entered (project manager) | 60% |
| E. Actual cost | Entered (hours × rate + purchases) | €184,000 |
| F. Planned value | B × C | €187,000 |
| G. Earned value | B × D | €132,000 |
| H. CPI | G ÷ E | 0.72 |
| I. SPI | G ÷ F | 0.71 |
| J. Margin at completion | A − B ÷ H | −€42,667 |

Add a total row that sums earned value and actual cost before dividing, never an average of the CPI column. The [Excel dashboard](https://www.datafuji.com/en/excel-dashboard) guide shows how to keep the file clean. The limit is the sources: timesheets, purchases and invoices have to be copied in every month.

### How much does a project dashboard cost?

In a spreadsheet or your project tool, the time it takes to build. In Power BI, the design, paid once, and the licenses, paid every month.

At Datafuji, the design is a fixed-price package of €3,000, €5,000 or €8,000 excl. VAT depending on the number of pages and sources, with an indicative lead time of 2 to 4 weeks ([packages](https://www.datafuji.com/en/pricing)). The example report (four pages, four sources) falls under the €5,000 package; without earned value, with only timesheets and invoices, under the €3,000 one.

The author and every reader need a Power BI Pro license, at €12.10 excl. VAT per user per month, paid yearly ([Power BI dashboard](https://www.datafuji.com/en/power-bi-dashboard)). For the engineering firm’s five people, author included, the first year costs 5,000 + 5 × 12.10 × 12 = €5,726 excl. VAT, licenses at French list prices. That is less than the HVAC project’s 1,033 unpaid hours, valued at €70: more than €72,000.

The lead time depends mostly on read access to timesheets, accounting and invoicing, and on a project code shared by all three.

With this dashboard, at the end of October, the HVAC project tops the list. The committee no longer discusses the month’s margin: it decides which change order to negotiate and which team to strengthen.

## Frequently asked questions

### What are the 3 types of dashboards?

Strategic, tactical and operational, based on Robert N. Anthony’s three levels of decision-making (1965). No standard defines this classification. An analytical dashboard, which explains a variance, is often added. In project management, we also distinguish the single-project dashboard, read every week by the project manager, from the portfolio dashboard, read every month by leadership.

### What are the 5 phases of a project?

The PMBOK Guide of the Project Management Institute (PMI), in its sixth edition, organizes a project’s processes into five process groups: initiating, planning, executing, monitoring and controlling, and closing. The dashboard belongs to the fourth: it compares execution against the plan. The seventh edition (2021) is organized around twelve principles, the eighth (2025) around six principles and seven performance domains.

### What is a good utilization rate?

One that covers your costs, which the hourly rate calculator works out for you: no public statistics report utilization rates by profession. Count the hours spent beyond a fixed-price budget separately: they inflate the rate without being paid for.

### How do you create a project dashboard?

Start with a project code and work packages shared by timesheets, purchases and invoices, then write down a progress rule. Next, set an hourly cost rate and a monthly status date. Finally, calculate each project on its own, and the portfolio from totals.

Sources

- U.S. Department of Energy, [DOE EVMS Gold Card](https://www.energy.gov/sites/default/files/2019/03/f60/DOE%20EVMS%20Gold%20Card%2020190308.pdf), March 8, 2019 (definitions of PV, EV, AC, BAC, CV, SV, CPI, SPI and EAC formulas), accessed November 10, 2026.

- U.S. Government Accountability Office, [Cost Estimating and Assessment Guide (GAO-20-195G), Project Future Performance](https://gaoinnovations.gov/cost-guide/project-future-performance.html) (generic EAC formula, table 24, CPI stability after 20% completion, SPI at program end), accessed November 10, 2026, address checked November 28, 2026.

- ISO 21508:2026, Project, programme and portfolio management – Earned value management, in force since February 6, 2026, replaces ISO 21508:2018: listing by the Estonian standards body, [evs.ee](https://evs.ee/en/iso-21508-2026), accessed November 10, 2026 (the iso.org listing could not be accessed that day). We have not read the standard itself, which is not freely available.

- Microsoft Support, [BCWP (Earned Value or EV) fields](https://support.microsoft.com/en-us/topic/bcwp-fields-e0c570ea-9c7b-4864-8a6b-920ed0f7b847) (“budgeted cost of work performed,” also known as earned value; Project 2016 to 2024 and Project Online Desktop Client), accessed November 28, 2026.

- Odoo, documentation 19.0, [Project dashboard](https://www.odoo.com/documentation/19.0/applications/services/project/project_management/project_dashboard.html), accessed November 10, 2026.

- Banque de France, [Fascicules d’indicateurs sectoriels](https://www.banque-france.fr/fr/publications-et-statistiques/statistiques/fascicules-dindicateurs-sectoriels) (sector indicator reports, in French), year 2024, published November 27, 2025 (FIBEN database, data available October 2025), divisions [62](https://www.banque-france.fr/system/files/2025-11/fascicule-sectoriel-conseil-62-2024.pdf), [71](https://www.banque-france.fr/system/files/2025-11/fascicule-sectoriel-architecture-71-2024.pdf), [73](https://www.banque-france.fr/system/files/2025-11/fascicule-sectoriel-publicite-73-2024.pdf), [43](https://www.banque-france.fr/system/files/2025-11/fascicule-sectoriel-construction-special-43-2024.pdf), page 3, 2024 column, and [methodology note](https://www.banque-france.fr/system/files/2025-11/methodologie-fascicules-sectoriels.pdf) (FIBEN covers companies with revenue above €1.25 million), accessed November 10, 2026, methodology reread November 28, 2026.

- Microsoft, [Power BI pricing](https://www.microsoft.com/en-ie/power-platform/products/power-bi/pricing) (Ireland page, in English: Power BI Pro at €12.10 per user per month, paid yearly, excl. VAT, the same price as on the French page checked November 3, 2026), checked November 28, 2026.

- O. de La Villarmois and H. Tondeur, [Une analyse des finalités des systèmes de contrôle](https://shs.hal.science/halshs-00587790v1) (in French), 20th congress of the Association francophone de comptabilité, 1999, HAL open archive (Robert N. Anthony’s three levels of control, 1965), accessed November 10, 2026.

- Wikipedia, [Project Management Body of Knowledge](https://en.wikipedia.org/wiki/Project_Management_Body_of_Knowledge) (five process groups: Initiating, Planning, Executing, Monitoring and Controlling, Closing; seventh edition 2021: 12 principles; eighth edition 2025: 6 principles and 7 performance domains), accessed November 20, 2026.