- [Home](https://www.datafuji.com/en)

- Construction

# Construction job costing: KPIs, percentage-of-completion margin and a job cost dashboard

Published November 28, 2026 · Updated November 28, 2026 · 15 min read

[Dylan Arnaud](https://www.datafuji.com/en/about#dylan-arnaud), founder of Datafuji

Job cost tracking compares, every month and for each work package, the budget, the cost to date and the cost to complete, so you know a job’s margin before the work ends. On a €1,200,000 contract (excl. VAT), €605,000 spent to date and €464,000 of cost to complete leave a €131,000 margin at completion: 10.9% of the price, against 14.2% planned.

## What is construction job cost tracking?

Job tracking covers two disciplines: technical tracking (schedule, quality, punch list, safety) and financial tracking, or job costing. The latter answers one question: is the job making the money planned in the estimate, and is that money coming in?

Five terms come up everywhere:

- the work package, the part of the contract assigned to one trade;

- the change order, which amends the signed contract and its price;

- the direct cost, the cost budgeted in the estimate, excluding overhead;

- the cost to complete, what still has to be spent to finish;

- the progress billing, the monthly interim invoice (pay application).

Every month, financial tracking answers four questions, in this order:

- What will the job cost once finished? Cost to date plus cost to complete, package by package: the estimate at completion.

- What margin will it leave? The price, including signed change orders, minus the estimate at completion.

- How far along is it? Percent complete, and the share of the margin already earned to date.

- Is it billed and paid? Billings against work performed, then cash collected, net of retainage.

An overrun spotted in the fourth month can still be negotiated (change order, resequencing, purchasing); spotted at year-end, it can no longer be recovered. And a healthy overall margin can hide one package that is slipping: tracking is done by package.

The company in our example is fictitious: a structural contractor, an SME with €13.6M in revenue over twelve months and eight jobs in progress at the end of October. We follow one of them throughout, a light industrial building under a private contract: €1,180,000 excl. VAT plus a €20,000 signed change order, five work packages.

## Which KPIs should you track on a construction job?

A construction company runs its jobs with about ten indicators. Margin at completion and percent complete measure profitability; underbillings and retainage, cash; hours and purchases, field management.

Values are the example company’s at the end of October; general definitions are in our [KPI library](https://www.datafuji.com/en/kpi#library).

| KPI | Formula | In the company | Most common pitfall |
| --- | --- | --- | --- |
| Estimate at completion | Cost to date + cost to complete, by package | €1,069,000 for the light industrial building | Leaving the cost to complete at the original budget instead of re-estimating it. |
| Variance to budget by package | Package estimate at completion − package budget | Structural work: +€24,000 | Looking only at the total, where one package offsets another. |
| Margin at completion | Price, including signed change orders − estimate at completion | €131,000, 10.9% of the price | Counting an unsigned change order: the total contract price must be identifiable without ambiguity (article 622-5 of the French chart of accounts). |
| Percent complete (cost-to-cost) | Cost to date ÷ estimate at completion | 56.6% | An underestimated cost to complete inflates percent complete. |
| Earned margin to date | Margin at completion × percent complete | €74,139 | Calculating it on billings. |
| Underbillings | Revenue earned to date − progress billings issued | €183k across the eight jobs | Treating an overbilling as margin. |
| Hours against budget | Hours worked ÷ estimate hours prorated to percent complete − 1 | 5,420 h in October for 5,110 h planned at this stage (+6.1%) | Comparing with the estimate’s total hours. |
| Retainage receivable | Sum of retainage, by acceptance date | €318k, of which €74k can be released this quarter | Waiting for it to come back on its own. |
| [DSO](https://www.datafuji.com/en/tools/dso-calculator) (days sales outstanding) | Receivables incl. VAT ÷ revenue incl. VAT × 365 | 64 days, against a 55-day target | Dividing receivables incl. VAT by revenue excl. VAT. |
| Backlog | Work remaining ÷ average monthly revenue | €4,467k ÷ €1,133k = 3.9 months | Including unsigned bids. |
| Markup factor (K coefficient) | Price ÷ budgeted direct cost | 1.165 at budget, 1.123 at completion | Reading it as profit: it must first cover overhead. |

Here the backlog only counts jobs in progress. All these formulas add up euros before dividing: a portfolio margin is never calculated by averaging the jobs’ percentages.

## How do you calculate a job’s margin before the work is finished?

The margin on a job in progress is calculated in two steps: the margin at completion, price minus cost to date and cost to complete, then the earned margin, that margin multiplied by percent complete. Both are recalculated every month.

Estimate at completion = cost to date + cost to complete Margin at completion = price (incl. signed change orders) − estimate at completion Percent complete (cost-to-cost) = cost to date ÷ estimate at completion Earned margin to date = margin at completion × percent complete

### The worked example, step by step

The light industrial building, end of October. Price: €1,180,000 + €20,000 signed change order = €1,200,000 excl. VAT. Budget for the five packages, updated for the change order: €1,030,000, a planned margin of €170,000 (14.2%).

Estimate at completion = 605,000 + 464,000 = €1,069,000 Margin at completion = 1,200,000 − 1,069,000 = €131,000 (10.9%) Percent complete = 605,000 ÷ 1,069,000 = 56.6% Revenue earned to date = 1,200,000 × 605,000 ÷ 1,069,000 = €679,139 Earned margin to date = 131,000 × 605,000 ÷ 1,069,000 = €74,139 Check = 679,139 − 605,000 = €74,139

With the exact, unrounded percent complete, the two calculations always tie out: that is a dashboard’s first check. The next question is where the €39,000 overrun comes from.

![Horizontal bars for the five work packages of the light industrial building, on the same scale. For each package, the budget as a gray line and the estimate at completion in blue: cost to date solid, cost to complete dotted. Structural work exceeds its budget by €24,000, halfway through; earthworks, finished, by €11,000; site setup and roofing by €2,000 each; framing is on budget. In total, €1,069,000 estimate at completion for a €1,030,000 budget: a €39,000 overrun.](https://www.datafuji.com/img/en/secteurs-btp-construction/secteurs-btp-construction-01.svg)

*Cost to date plus cost to complete: a €39,000 overrun, €24,000 of it on structural work alone.*

Earthworks are finished, so their variance is locked in. The structural work variance, halfway through, can still be discussed with the project manager.

### Cost-to-cost or physical percent complete?

Percent complete can be measured on costs, cost to date ÷ estimate at completion, or in the field, from quantities installed. The French chart of accounts allows both (article 622-3), as do the input and output methods of ASC 606 and IFRS 15, and comparing them is the best detector of an overly optimistic cost to complete.

On structural work, €268,000 has been spent out of €444,000 expected at completion: 60.4% of costs. The project manager measures 55% of the work completed on site.

If 55% is right: Package cost = 268,000 ÷ 0.55 = €487,273 True cost to complete = 487,273 − 268,000 = €219,273 (not 176,000)

Comparing the two measures shows where the gap is hiding.

![Two gauges from 0 to 100% for the structural work package. In orange, cost-to-cost percent complete: €268,000 spent out of €444,000 expected, 60.4%, which assumes €176,000 of cost to complete. In green, physical percent complete observed in the field: 55%, which implies a package cost of €487,273 and €219,273 of cost to complete. The 5.4-point gap signals a cost to complete underestimated by €43,273.](https://www.datafuji.com/img/en/secteurs-btp-construction/secteurs-btp-construction-02.svg)

*Costs are running ahead of the work: the structural cost to complete is €43,273 short.*

When the gap exceeds five points, ask the project manager. Here, the job’s cost would rise to €1,112,273 and its margin fall to €87,727.

### A margin on direct cost is not a profit

The margin at completion is a margin on direct cost: it still has to pay for overhead, from engineering to management salaries. The markup factor, or K coefficient, shows it: 1,200,000 ÷ 1,030,000 = 1.165 at budget, 1.123 at completion.

A job is profitable when its margin on direct cost exceeds overhead as a percentage of revenue. If overhead exceeds 10.9% of revenue, the light industrial building no longer contributes to profit, even though its margin is still positive.

That percentage comes from [cost accounting](https://www.datafuji.com/en/cost-accounting), and the break-even point follows from it: overhead ÷ margin rate on direct cost. The [cost price calculator](https://www.datafuji.com/en/tools/cost-price-calculator) takes you from direct cost to selling price.

## What does French GAAP say about percentage-of-completion margin?

For a contract spanning at least two fiscal years, the French chart of accounts (plan comptable général) allows either the completed-contract or the percentage-of-completion method, but in both cases requires a provision for any probable loss (articles 622-1 to 622-7).

### Two methods to choose from

- Completed contract: revenue and profit are recognized when the work is completed; along the way, work in progress is recorded up to the costs incurred (article 622-2).

- Percentage of completion: the profit recognized is the profit at completion multiplied by percent complete (article 622-3).

Percentage of completion is not one of the “preferred methods” (article 121-5): it is the company’s choice, applied to all its contracts in progress (article 622-7). The dashboard, for its part, tracks the earned margin in both cases: only the earned margin tells you each month what the job is making. In the United States and under IFRS, revenue on such contracts is generally recognized over time (ASC 606, IFRS 15).

The company must still know total revenue and costs, and have “management, cost accounting and internal control tools” (article 622-5). Otherwise, revenue is limited to the costs incurred (article 622-4). Job cost tracking is that tool.

### Billings are not revenue

The light industrial building has issued €720,000 of progress billings, for revenue earned to date of €679,139. A generous pay application does not create margin.

![Two bars on the same scale for the light industrial building. Revenue earned to date, €679,139, is made of €605,000 of cost to date and €74,139 of margin, in green. Progress billings reach €720,000: the €40,861 above revenue, in orange, are billed in advance, deferred revenue (French account 487), not margin.](https://www.datafuji.com/img/en/secteurs-btp-construction/secteurs-btp-construction-03.svg)

*€720,000 billed for €679,139 earned: €40,861 is an advance from the customer, not a gain.*

In the accounts, this surplus is neutralized, most often as deferred revenue (account 487 in France): in the US, billings in excess of costs and estimated earnings, or overbillings. Conversely, work performed but not billed goes to unbilled receivables (account 4181), the underbillings. Across the company’s eight jobs, net underbillings reach €183k: cash waiting for an invoice.

### A job in a loss position: the provision

“The probable overall loss is provided for, less any losses already recognized” (article 622-6). Suppose the structural cost to complete rises from €176,000 to €330,000. The job had already recognized €74,139 of earned margin: it is reversed in the same month.

Estimate at completion = 605,000 + 618,000 = €1,223,000 Loss at completion = 1,200,000 − 1,223,000 = −€23,000 Percent complete = 605,000 ÷ 1,223,000 = 49.5% Loss recognized = 23,000 × 605,000 ÷ 1,223,000 = €11,378 Provision = 23,000 − 11,378 = €11,622 Margin already recognized, reversed = €74,139 Impact on the month’s profit = −74,139 − 11,378 − 11,622 = −€97,139

The chart contrasts two ways of recording this loss.

![Two timelines of the monthly profit of a loss-making job, from the month the loss becomes probable to acceptance. At the top, in orange, the wrong practice: the €23,000 loss spread as small losses month after month. At the bottom, in green, the French chart of accounts rule (article 622-6): the whole loss in the month it becomes probable, €11,378 of loss recognized by percent complete plus an €11,622 provision; the following months stay at zero. In the same month, the €74,139 margin already recognized is reversed: the month’s profit falls by €97,139.](https://www.datafuji.com/img/en/secteurs-btp-construction/secteurs-btp-construction-04.svg)

*The whole loss goes into the month it becomes probable, with the reversal of the margin already recognized: €97,139 off the month’s profit.*

The owner sees it in that month’s profit, not at acceptance: hence the value of re-estimating the cost to complete every month.

## How do you calculate a progress billing?

A progress billing is the contractor’s monthly interim invoice, calculated on a cumulative basis. It starts from the work performed since the beginning, deducts the previous billing, adds VAT, then deducts retainage if the contract provides for it.

The cumulative basis corrects a previous month’s error by itself. For the light industrial building, billings go from 52% to 60% of €1,200,000 excl. VAT; VAT at 20% (the French standard rate), 5% retainage on the amount incl. VAT:

| Line | Cumulative to date | Previous billing | This month |
| --- | --- | --- | --- |
| Work excl. VAT | €720,000 | €624,000 | €96,000 |
| VAT | €144,000 | €124,800 | €19,200 |
| Work incl. VAT | €864,000 | €748,800 | €115,200 |
| Retainage | −€43,200 | −€37,440 | −€5,760 |
| Net amount due | €820,800 | €711,360 | €109,440 |

Check: 820,800 − 711,360 = €109,440. The amount left to bill falls to €480,000 excl. VAT. At the end of the job, retainage will reach €72,000 (5% of €1,440,000 incl. VAT).

### Retainage in French private contracts

In France, law no. 71-584 of July 16, 1971 allows interim payments to be reduced by a “retention of no more than 5 percent of their amount,” which secures the correction of punch-list items (article 1). The owner places it in escrow, or the contractor provides a bank guarantee instead.

One year after acceptance, the guarantee is released or the withheld sums are paid, unless a reasoned objection is served by registered letter (article 2). Any clause to the contrary is void (article 3), including in subcontracting (article 4). The law does not say whether the “amount” is before or after VAT: the contract decides.

## Public and private contracts in France: what changes?

A French public contract is governed by the public procurement code, which sets interim payments, advances, retainage and payment terms. A private contract is governed by its own terms, within the framework of the Civil Code, the Commercial Code and the 1971 law.

| Topic | Public contract | Private business-to-business contract |
| --- | --- | --- |
| Interim payments | Equal to the value of the work, less retainage; at intervals of no more than three months, monthly for an SME on a works contract (R2191-20 to R2191-22) | Frequency set by the contract; monthly progress billing is customary |
| Retainage | At most 5% of the initial amount, change orders included; 3% for an SME on a contract with the State or a public buyer with more than €60M in operating expenditure (R2191-33) | At most 5% of interim payments, held in escrow or replaced by a guarantee (1971 law) |
| Advance payment | Mandatory above €50,000 excl. VAT and two months of performance (R2191-3): 5 to 30% of the amount incl. VAT, at least 30% for an SME on a State contract, 10% with large public buyers (R2191-7) | As set by the contract |
| Payment terms | 30 days; 50 for public health institutions, 60 for state-owned companies (R2192-10 and R2192-11) | No more than 60 days after the invoice, or 45 days end of month if the contract says so; 30 days if the contract is silent (L441-10 of the Commercial Code) |
| Payment guarantee | Not applicable | Required from the owner above €12,000 excl. VAT; without it, an unpaid contractor may suspend work fifteen days after a formal notice that goes unanswered (article 1799-1 of the Civil Code, decree no. 99-658) |
| Price adjustment | Through an index, a formula representative of cost, or both (R2112-13); mandatory for contracts longer than three months when raw materials follow world prices (R2112-14) | As set by the contract, often on INSEE’s BT or TP indexes |

The article 1799-1 guarantee does not apply when the owner is a private individual having work done for personal needs.

### INSEE’s BT and TP indexes

INSEE (the French national statistics office) publishes monthly building cost indexes (BT01, all trades, then one per trade) and public works indexes (TP01), base 100 in 2010, which are used in price adjustment clauses.

| Index | September 2025 | September 2026 | Over one year |
| --- | --- | --- | --- |
| BT01, building, all trades | 133.3 | 139.1 | +4.4% |
| TP01, public works | 130.7 | 142.0 | +8.6% |

With the simplest formula, with no fixed portion, €400,000 excl. VAT of work priced at September 2025 conditions and performed in September 2026 becomes 400,000 × 139.1 ÷ 133.3 = €417,404. Your contract sets its own formula.

The indexes are published with a lag of about two months: the September 2026 values appeared in the Journal officiel (France’s official gazette) on November 15.

## What public benchmarks are there for a construction company?

In France, the Banque de France and INSEE publish ratios for construction companies: drawn from annual accounts, they let you benchmark your profitability, payment periods and working capital requirement, but none measures a job margin.

### Banque de France ratios

The 2024 “Construction” report covers 29,551 French companies with median revenue of €3.2M. The quartiles show the weakest quarter, the company in the middle and the strongest quarter.

| Ratio | Formula | 1st quartile | Median | 3rd quartile |
| --- | --- | --- | --- | --- |
| Change in revenue excl. VAT | Change in revenue ÷ prior-year revenue | −9.9% | 0.8% | 12.6% |
| Value added rate | Value added ÷ (production + sales of goods) | 30.6% | 39.2% | 47.4% |
| Profit share | Gross operating surplus (EBE) ÷ value added | 9.6% | 18.8% | 30.5% |
| Gross overall surplus rate | Gross overall surplus ÷ revenue excl. VAT | 4.0% | 7.5% | 12.4% |
| Net customer payment period | (Receivables − advances received) ÷ revenue incl. VAT × 360 | 36.9 days | 61.4 days | 87.1 days |
| Net supplier payment period | (Payables − advances paid) ÷ purchases and external charges incl. VAT × 360 | 36.6 days | 52.2 days | 72.6 days |
| Operating working capital | Operating working capital requirement ÷ revenue excl. VAT × 360 | 0.3 days | 23.9 days | 49.6 days |

The Banque de France “profit share” divides gross operating surplus by value added: it cannot be compared with a job margin.

Operating working capital (23.9 days of revenue at the median) includes underbillings and retainage.

The example company recalculates its DSO on the same 360-day basis:

DSO, 360-day basis = 64 × 360 ÷ 365 ≈ 63 days

Plotted against the sector’s quartiles, its position is clear at a glance.

![Scale from 20 to 100 days of net customer payment periods in French construction in 2024, according to the Banque de France, on a 360-day basis: 36.9 days at the first quartile, 61.4 days at the median, 87.1 days at the third quartile. The example company, recalculated on 360 days (64 × 360 ÷ 365), is at about 63 days, just above the median, before deducting advances received.](https://www.datafuji.com/img/en/secteurs-btp-construction/secteurs-btp-construction-05.svg)

*On a 360-day basis, the company is paid about two days later than the median company in the sector.*

The gap remains approximate: the company has not deducted its advances received. The Banque de France’s twelve ratios and their quartiles for eleven sectors are in the [financial ratios calculator](https://www.datafuji.com/en/tools/financial-ratios).

### INSEE ratios

| Sector, 2023 | Value added rate | Profit share | Investment rate |
| --- | --- | --- | --- |
| Construction | 31.5% | 22.8% | 10.3% |
| All market sectors | 28.3% | 30.7% | 20.1% |

Aggregated across all companies, these ratios show a sector that keeps more value added than average, but less gross surplus: according to the Banque de France, employees receive 78.1% of the median company’s income. Hence the importance of hours worked, and of worker safety ([lost-time injury frequency and severity rates](https://www.datafuji.com/en/tools/ltifr-calculator)).

### Customer payment terms and insolvencies

- Customer payment terms. Excluding microbusinesses, French construction was paid in 59.7 days of revenue in 2025, against 41.5 across all sectors and 67.5 in 2007 (unweighted averages, on 360 days). The sector’s microbusinesses: 32.6 days.

- Insolvencies. Over the twelve months to the end of September 2026, 14,380 French construction companies entered insolvency proceedings, 2.7% fewer than a year earlier. That is 20% of the economy’s 71,139 insolvencies, a total up 4.4%.

The ratios date from 2024 and 2023 and mix property development, building and public works: aim for the median rather than the third quartile.

## What does a construction job dashboard look like?

A job dashboard fits into two reports. Management’s report ranks jobs by margin drift and tracks cash. The project managers’ report tracks hours and purchases before the end of the month.

The company’s management page first shows which jobs are drifting.

![Screenshot of the fictitious company’s “Management · Jobs” Power BI report, end of October: portfolio margin at completion of 10.8% against 11.9% at budget, earned margin to date of €721k out of €1,213k, one job out of eight in a loss position (the town hall, €11k provided for), and the table of the four jobs drifting the most.](https://www.datafuji.com/img/en/secteurs/btp-construction/exemple-clair.webp)

*Eight jobs, one page: the town hall loses 17.9 margin points, the light industrial building 3.2.*

The portfolio is worth €11.2M in contract value; its margin at completion has been falling since May, and the table at the bottom says why. The four pages of the two reports:

| Report | Reader and frequency | The question | Its indicators, end of October |
| --- | --- | --- | --- |
| Management · job margins | Owner, CFO, project managers; monthly review | Which jobs are drifting from their budget? | Margin at completion 10.8% (11.9% at budget); earned margin €721k; 1 job in a loss position out of 8 |
| Management · billing and customers | Owner, CFO; monthly review | Is the work performed billed and collected? | Underbillings €183k (target €100k); DSO 64 days (target 55); retainage receivable €318k |
| Field management · hours | Project managers and construction manager; throughout the month | Are hours within budget? | 5,420 h worked for 5,110 h (+6.1%); fully loaded hourly cost €38.40; 4.2% of hours without a job code |
| Field management · purchasing | Same readers; throughout the month | Are purchases within the estimate’s prices? | €612k committed for €587k (+4.3%); equipment rental €71k for €62k (+14.5%); 46 invoices without a purchase order |

On the purchasing page, a crane kept two weeks too long shows up before its invoice. The data refreshes every night; margins are final after the cost-to-complete review.

### Data sources in a construction SME

Four sources are enough, but they do not describe the job in the same way.

| Source | What it provides | The trap |
| --- | --- | --- |
| Estimate and budget | The price, the packages, the budgeted direct cost (hours, materials, subcontracting, equipment) | A budget never updated for change orders: the price goes up, not the budget, and the margin looks better than it is |
| Timesheets | Hours by worker, by day and by job, valued at the fully loaded hourly cost | Hours without a job code, or entered from memory at the end of the week |
| Purchasing and subcontracting | Purchase orders (committed cost), receipts, invoices, subcontracts | An invoice without a purchase order, charged to the wrong job or received after the month-end close |
| Accounting | The authoritative cost to date, billings, collections, retainage | Costs without a job code: they exist in the accounts, not in job tracking |

Reconciliation comes down to one rule: a single job code, the same in the estimating software, timesheets, purchase orders and accounting, and if possible a package code. Second check: the cost to date of all jobs must tie back to the month’s costs, apart from overhead, shown separately.

The fully loaded hourly cost is calculated with the [hourly rate calculator](https://www.datafuji.com/en/tools/hourly-rate-calculator) ; data from business software is read by [connecting Power BI to an ERP](https://www.datafuji.com/en/power-bi-erp) and organized as a [star schema](https://www.datafuji.com/en/star-schema).

### What software should you use to track your jobs?

Three types of tools share the work. Construction management software handles estimates, progress billings, sometimes hours and purchasing. Mobile field apps hold daily reports, photos and punch lists. The analysis tool, finally, is Excel or Power BI.

A free app or an Excel template handles a schedule or a punch list well, but rarely calculates an estimate at completion by package, for lack of a cost to complete and a link to the accounts.

Before any project, check three things in your management software: whether it can record a cost to complete by package, export the data, and share a job code with accounting.

| Your situation | The simplest option |
| --- | --- |
| The job management software records estimates, hours, purchases and costs to complete | Its own reports |
| Three or four jobs a year, one owner who handles everything | An [Excel dashboard](https://www.datafuji.com/en/excel-dashboard), one tab per job |
| Estimates, timesheets, purchasing and accounting in different tools | Power BI, which matches them by job code and refreshes every night |
| Several branches or companies to compare | Power BI, with the same definitions and access rights by branch |

The cost of such a project, licenses included, is on our [pricing](https://www.datafuji.com/en/pricing) page.

At the next review, structural work is no longer “on track” on the strength of its cost to date: everyone sees its estimate at completion, and the change order is decided before acceptance. Among the other [dashboards](https://www.datafuji.com/en/dashboard), the [financial dashboard](https://www.datafuji.com/en/financial-dashboard) tracks profit and cash; an engineering firm will prefer the [project dashboard](https://www.datafuji.com/en/project-dashboard).

## Frequently asked questions

### How do you track job costs on a construction project?

Give each job a single code, the same in estimates, timesheets, purchase orders and accounting. Then ask the project manager each month for a cost to complete for each work package. Finally, package by package, compare the estimate at completion with the budget, and billings with percent complete.

### What is the average margin in construction?

Public ratios do not measure job margin. The closest one, the Banque de France’s gross overall surplus rate (gross overall surplus ÷ revenue excl. VAT), was 7.5% for the median French construction company in 2024: 4.0% at the first quartile, 12.4% at the third. They cover the whole construction sector, masonry included, without a rate for each trade.

### What is a construction schedule?

The plan of the work over time, often drawn as a Gantt chart; in French public contracts, it is called the execution schedule. It runs from preparation to acceptance, the act by which the owner accepts the work with or without punch-list items (in France, article 1792-6 of the Civil Code).

### What does TCE mean in French construction?

TCE stands for “tous corps d’état,” all trades: a contract or a company that covers every work package of a building, from structural work to finishes, rather than a single trade. It is close to what English speakers call a general contractor. INSEE’s BT01 index tracks the change in their costs.

Sources

- Autorité des normes comptables (French accounting standards authority), [Plan comptable général, consolidated version as of January 1, 2026](https://www.anc.gouv.fr/files/anc/files/1_Normes_fran%C3%A7aises/recueil/2026/PCG--1er-janvier-2026.pdf) (in French), articles 121-5, 622-1 to 622-7 and chart of accounts (4181, 487), accessed November 10, 2026.

- Légifrance, [Law no. 71-584 of July 16, 1971 regulating retainage in works contracts](https://www.legifrance.gouv.fr/loda/id/JORFTEXT000000687670) (in French), articles 1 to 4, current version, accessed November 10, 2026.

- Légifrance, [French public procurement code](https://www.legifrance.gouv.fr/codes/section_lc/LEGITEXT000037701019/) (in French), articles R2112-13, R2112-14, R2191-3, R2191-7, R2191-20 to R2191-22, R2191-33, R2192-10 and R2192-11, current versions, accessed November 10, 2026.

- Légifrance, [French Civil Code, article 1799-1](https://www.legifrance.gouv.fr/codes/article_lc/LEGIARTI000027645885), and [decree no. 99-658 of July 30, 1999, article 1](https://www.legifrance.gouv.fr/codes/article_lc/LEGIARTI000029716750) (€12,000 excl. VAT threshold) (in French), accessed November 10, 2026.

- Légifrance, [French Commercial Code, article L441-10](https://www.legifrance.gouv.fr/codes/article_lc/LEGIARTI000038414392) (in French), version in force since April 26, 2019, accessed November 10, 2026.

- INSEE (French national statistics office), macroeconomic database, [BT01 index](https://www.insee.fr/fr/statistiques/serie/001710986) and [TP01 index](https://www.insee.fr/fr/statistiques/serie/001711007) (in French), base 2010, final values for September 2025 and September 2026, the latter published in the Journal officiel on November 15, 2026, accessed November 20, 2026.

- Banque de France, [sector indicators report “F - Construction,” year 2024](https://www.banque-france.fr/system/files/2025-11/fascicule-sectoriel-construction-F-2024.pdf) (FIBEN database, data available in October 2025), via the page [Fascicules d’indicateurs sectoriels](https://www.banque-france.fr/fr/publications-et-statistiques/statistiques/fascicules-dindicateurs-sectoriels) (in French), accessed November 10, 2026, rechecked November 20, 2026.

- INSEE, [Ratios des secteurs marchands par activité, données annuelles 2023](https://www.insee.fr/fr/statistiques/2015421) (Ésane, in French), accessed November 10, 2026.

- Banque de France, Olivier Gonzalez, [En 2025, les délais fournisseurs ont diminué pour toutes les catégories d’entreprises, mais des marges de progrès persistent](https://www.banque-france.fr/fr/publications-et-statistiques/publications/en-2025-les-delais-fournisseurs-ont-diminue-pour-toutes-les-categories-dentreprises-mais-des-marges) (in French), Bulletin de la Banque de France no. 266/5, October 16, 2026, table 2 and appendix 3, accessed November 10, 2026.

- Banque de France, [Défaillances d’entreprises, septembre 2026](https://www.banque-france.fr/fr/statistiques/entreprises/defaillances-dentreprises-2026-09) (in French), table A (twelve-month cumulative total, raw data), published November 6, 2026, accessed November 10, 2026, rechecked November 20, 2026.

- IFRS Foundation, [IFRS 15 Revenue from Contracts with Customers](https://www.ifrs.org/issued-standards/list-of-standards/ifrs-15-revenue-from-contracts-with-customers/), effective for annual periods beginning on or after January 1, 2018 (performance obligations satisfied over time; paragraph 35(b), work in progress the customer controls; paragraph 41, output methods and input methods), accessed November 28, 2026.

- Deloitte, DART, [Revenue roadmap, 8.5 Measuring Progress for Revenue Recognized Over Time](https://dart.deloitte.com/USDART/home/codification/revenue/asc606-10/roadmap-revenue-recognition/chapter-8-step-5-determine-when/8-5-measuring-progress-for-revenue) (ASC 606-10-25-33: output methods and input methods), accessed November 28, 2026.

- EisnerAmper, [ASC Topic 606: Contract Assets and Liabilities for the Construction Industry](https://www.eisneramper.com/insights/real-estate/contract-assets-liabilities-within-asc-topic-606-construction-industry-0622/), January 29, 2024 (billings in excess of costs and earnings as a contract liability, costs and estimated earnings in excess of billings as a contract asset), accessed November 28, 2026.